Research on Buffer Calculation Model of Critical Chain Based on Adjacency Information Entropy

Author:

Nie Xiangtian123,Li Min1,Lu Jilan1,Wang Bo1

Affiliation:

1. School of Water Conservancy, North China University of Water Resources and Electric Power, Zhengzhou 450046, China

2. Henan Collaborative Innovation Center for Water Efficient Utilization and Guarantee Engineering, Zhengzhou 450046, China

3. Henan Province Key Laboratory of Water Environment Simulation and Treatment, Zhengzhou 450046, China

Abstract

In project network planning, the correlation complexity of the processes is not only related to the immediately preceding and following processes, but also closely related to indirect adjacent processes. In the existing relevant studies, many scholars have considered the influence of direct adjacent processes but ignored the influence of indirect adjacent processes. In addition, the three-point time estimation method and Monte Carlo simulation are mostly used in the current research for the estimation of process duration, while less research exists on the estimation of process optimal duration under multi-objective constraints. Therefore, this paper proposes a buffer calculation model of critical chain based on adjacency information entropy. This methodology provides comprehensive consideration of the relationship between cost, quality, safety, environment and process duration, the influence of process’s resource demand intensity, resource constraints and process duration on the buffer size, the influence of the relay potential of mutual cooperation and cross construction between processes, as well as the influence of adjacent complexity of processes on the project construction schedule. The calculation example analysis shows that this method can improve the accuracy of the calculation of process safety time, reduce the influence of the complexity of process adjacency correlation on the project construction schedule, reasonably control the buffer size, and effectively shorten the planned project duration.

Publisher

MDPI AG

Subject

Building and Construction,Civil and Structural Engineering,Architecture

Reference41 articles.

1. Application of the Critical Chain Technique to the Project Scheduling Management;Bao;J. Lanzhou Jiaotong Univ.,2009

2. Project Cost, Progress and Quality Integrated Evaluation Based on Vector Angle Cosine;Chen;J. Civ. Eng. Manag.,2016

3. Goldratt, E.M. (1997). Critical Chain, The North River Press.

4. Review and Prospect of Buffer Sizing of a Critical Chain Project;Zhang;Manag. Rev.,2017

5. On the merits and pitfalls of critical chain scheduling;Herroelen;J. Oper. Manag.,2001

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3