Project Cost Overrun Risk Prediction Using Hidden Markov Chain Analysis

Author:

Leu Sou-Sen1,Liu Yanni1,Wu Pei-Lin1

Affiliation:

1. Department of Civil and Construction Engineering, National Taiwan University of Science and Technology, 43 Keelung Road, Section 4, Taipei 106, Taiwan

Abstract

Construction project cost overrun is a common problem in the construction industry. The cost of construction projects is thought to have increased by approximately 33% on average. Several types of research on construction project cost overrun have been conducted and these generally rely on historical data. However, whilst each project has its own project characteristics and cost trend, real-time project cost data are more reliable to forecast its own cost trend. This paper proposes a real-time hidden Markov chain (HMM) model to predict cost overrun risk based on project-owned cost performance data and the corrective actions if adopted. The cost overrun events occurrence in this model was assumed to follow a Poisson arrival pattern. Real-time HMM with a particle filter was used to run the simulation. One SRC building project in Taiwan was used for model validation and comparison. The posterior probabilities from the real-time HMM model were highly consistent with the cost overrun ratios of real construction projects. The proposed cost overrun prediction model could provide an early alert of cost overruns to the project manager. Based on the survey of cost overrun risk and significantly influential factors, we propose effective cost management plans to alleviate the frequency of project cost overrun.

Publisher

MDPI AG

Subject

Building and Construction,Civil and Structural Engineering,Architecture

Reference32 articles.

1. Construction cost factors in Nigeria;Elinwa;J. Constr. Eng. Manag. ASCE,1993

2. Hartley, J.R., and Okamoto, S. (1997). Concurrent Engineering: Shortening Lead Times, Raising Quality, and Lowering Costs, Productivity Press.

3. Forecasting final cost and budget of construction projects;Teicholz;J. Comput. Civ. Eng. ASCE,1993

4. Baccarini, D. (2006, January 11–14). The maturing concept of estimating project cost contingency—A review. Proceedings of the 31st Australasian University Building Educators Association Conference (AUBEA 2006): Building in Value, Sydney, Australia.

5. Probabilistic monitoring of project performance using SS-curves;Barraza;J. Constr. Eng. Manag. ASCE,2000

Cited by 3 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3