A Dynamic Model for Effective and Optimal Planning of Formwork in Construction Projects

Author:

Baskova Renata1,Tazikova Alena1ORCID,Strukova Zuzana1ORCID,Kozlovska Maria1ORCID,Cabala Jozef1

Affiliation:

1. Institute of Technology, Economics and Management in Construction, Faculty of Civil Engineering, Technical University of Košice, 042 00 Košice, Slovakia

Abstract

The cost of producing one cubic meter of concrete structure, depending on the structure’s shape, type, and complexity, can be variously high. The cost of concrete, reinforcement, formwork, and labor ratio varies. But unlike the cost of concrete and reinforcement, which tend to be similar in the terms of the conditions of a particular construction project, the cost of formwork and work with it are different for different contractors. It often depends on the appropriateness of the formwork system used, the optimal placement of the formwork sets, the minimization of downtime, and the efficiency of the carpenters’ work. Formwork modeling in the construction preparation phase intervenes in this planning area, where construction sources are defined and quantified, and the time course of their deployment is determined. The current paper deals with optimizing formwork selection and deployment in concrete structure execution. Even if several requirements must be considered when selecting and modeling the formwork (e.g., construction time, quality of concrete structure, etc.), an effort to minimize the cost of formwork, and thus construction cost, plays the most significant role. A dynamic model for effective and optimal planning of formwork in construction projects, including formwork cost analysis, is presented in the paper. The included case study demonstrated the planning of the formwork through a software application developed based on the computational algorithm of the dynamic model presented. A case study is presented in the article as a research method. An office building with five above-ground floors and one underground floor was chosen for the case study. To solve the case study, the formwork for horizontal structures (i.e., beams and slabs) is considered. The goal of the case study is to identify research questions and apply time and cost optimization to a selected specific building.

Funder

VEGA

Publisher

MDPI AG

Subject

Building and Construction,Civil and Structural Engineering,Architecture

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3