Hydraulic Transient Impact on Surrounding Rock Mass of Unlined Pressure Tunnels

Author:

Ghimire Sanyam1ORCID,Panthi Krishna Kanta1ORCID,Vereide Kaspar2ORCID

Affiliation:

1. Department of Geoscience and Petroleum, Norwegian University of Science and Technology (NTNU), Petroleumsteknisk Senter, F 410, Valgrinda, S.P. Andersens Vei 15a, 7031 Trondheim, Norway

2. Department of Civil and Environmental Engineering, Norwegian University of Science and Technology (NTNU), Vassbygget, 322, Valgrinda, S.P. Andersens Veg 5, 7031 Trondheim, Norway

Abstract

The frequent pressure pulsations due to hydraulic transients in hydropower plants induce cyclic loading on the rock mass that may contribute to increased instances of block falls and increased risk of tunnel collapse over the power plant lifetime. This study focuses on understanding the effect of frequent start and stop sequences of hydropower in unlined pressure tunnels. For this purpose, data from a pore water pressure monitoring system is utilized, which was installed at the downstream end of the headrace tunnel at the 50 MW Roskrepp hydropower plant in southern Norway. The objective of this study is to analyze the recorded data and quantify the impact of the hydraulic transient on the surrounding rock mass in the unlined pressure tunnel. The monitoring of pressure data over several years clearly shows that frequent load changes could cause a considerable effect on the rock mass and constituent joint system. A delayed response of the pressure in boreholes in the rock mass compared with inside the tunnel is seen in all start and stop sequences and is considered to be the main reason for instability caused by transients. The response of pore pressure in boreholes is greatly influenced by the characteristics of joints. The results show that the start sequence and shorter shutdown duration exert a greater impact on rock mass as compared to the stop sequence and longer shutdown duration. Therefore, it is recommended to increase the shutdown duration so that the impact can be minimized to increase the tunnel lifetime. This study recommends implementing a more conservative design approach in tunnels with weak rock masses in projects that involve frequent load changes.

Funder

HydroCen research centre

Publisher

MDPI AG

Subject

Water Science and Technology,Aquatic Science,Geography, Planning and Development,Biochemistry

Reference33 articles.

1. Panthi, K.K., and Basnet, C.B. (November, January 29). State-of-the-art design guidelines in the use of unlined pressure tunnels/shafts for hydropower scheme. Proceedings of the ISRM International Symposium—10th Asian Rock Mechanics Symposium, ARMS 2018, Singapore.

2. Rancourt, A.J. (2010). Guidelines for Preliminary Design of Unlined Pressure Tunnels. [Ph.D. Thesis, McGill University].

3. Deregulation of Electricity Markets: The Norwegian Experience;Bye;Econ. Political Wkly.,2005

4. Eurelectric (2011). Hydro in Europe: Powering Renewables, Eurelectric. Technical Report.

5. Skar, C., Jaehnert, S., Tomasgard, A., Midthun, K., and Fodstad, M. (2018). A Position Paper Prepared by FME CenSES, CenSES Centre for Sustainable Energy Studies.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3