Delay Causes and Types in Nigerian Power Construction Projects

Author:

Ismaila Usman,Jung Wooyong,Park Chan Young

Abstract

Numerous events cause delays to entire power projects’ completion timelines, leading to loss. This paper focuses on revealing the critical delay causes in Nigerian power projects and identifying the delay types such as excusable delay, compensable delay, critical delay, and concurrent delay from the different perspectives of owner and contractor. Based on the survey of the 84 industrial experts in power distribution and transmission projects in Nigeria, this study provides the mean score and rank of 39 delay causes. Among the causes, 14 are identified as critical in the Nigerian power project. The top three critical delay causes are corruption and bureaucracy in government, inadequate fund/budget allocation, and price fluctuation/inflation. Owner and contractor do not show the difference in classifying the 14 delay causes into excusable and compensable delays. However, there was a difference between owner and contractor in categorizing whether a cause is critical or not and concurrent or not. A different viewpoint of types of delay cause can lead to a dispute which may lead to other delays and losses, and thus it is meaningful to understand the types of delay perceived from owner and contractor. Even though the delay cause and types are different depending on an individual project, the results of this study serve as a reference and would be beneficial for the practitioners in the construction industry to help identify the delay causes to manage them effectively.

Funder

National Research Foundation of Korea

KEPCO International Nuclear graduate School

Publisher

MDPI AG

Subject

Energy (miscellaneous),Energy Engineering and Power Technology,Renewable Energy, Sustainability and the Environment,Electrical and Electronic Engineering,Control and Optimization,Engineering (miscellaneous)

Reference25 articles.

1. Project Management in Nuclear Power Plant Construction: Guidelines and Experience,2012

2. Causes and Effects of Cost Overruns in Public Building Construction Projects Delivery, In Imo State, Nigeria

3. Transforming the Nigerian power sector for sustainable development

4. Causes of Delay in Project Construction in Developing Countries;Vyas;Indian J. Commer. Manag. Stud.,2013

5. Large construction projects in developing countries: a case study from Vietnam

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3