Analysis of Causes of Delays and Cost Overruns as Well as Mitigation Measures to Improve Profitability and Sustainability in Turnkey Industrial Projects

Author:

Álvarez-Pozo Antonio Héctor12,Parma-García Miguel Ignacio123ORCID,Ortiz-Marcos Isabel3ORCID,Bautista Luis Fernando45ORCID,Atanes-Sánchez Evangelina1ORCID

Affiliation:

1. Department of Mechanical, Chemical and Industrial Design Engineering, Escuela Técnica Superior de Ingeniería y Diseño Industrial, Universidad Politécnica de Madrid, 28012 Madrid, Spain

2. Técnicas Reunidas S.A., 28050 Madrid, Spain

3. Department of Organization Engineering, Business Administration and Statistics, Escuela Técnica Superior de Ingenieros Industriales, Universidad Politécnica de Madrid, 28006 Madrid, Spain

4. Department of Chemical and Environmental Technology, ESCET, Universidad Rey Juan Carlos, 28933 Móstoles, Spain

5. Instituto de Tecnologías para la Sostenibilidad, Universidad Rey Juan Carlos, 28933 Móstoles, Spain

Abstract

Delays and cost overruns in turnkey projects can lead to significant economic losses, disputes and even project abandonment. These facts negatively impact the environmental, social and governance (ESG) policies of companies involved in the project. In this paper, a bibliographic review was conducted to identify the leading causes of delays and cost overruns in turnkey industrial projects in the refining, gas and conventional electricity generation (RGE) sector and propose good practices to avoid or mitigate them. We identified 893 causes of delays and cost overruns and 147 mitigation measures. The causes and mitigation measures were grouped into eight categories based on the execution phases of an RGE project. A critical analysis was carried out to avoid duplication, and the result was evaluated by experts in turnkey project management, reducing the causes and mitigation measures to a final set of 103 and 49, respectively. The construction category showed the most significant influence on project delays and cost overruns, and this, together with the preliminary phase and project management categories, contributed to 60% of the identified causes. The findings of this study can help project managers improve the profitability of turnkey industrial projects, promoting innovation and sustainability within companies and society.

Publisher

MDPI AG

Reference42 articles.

1. Deloitte (2022). Global Powers of Construction 2022, Deloitte.

2. McKinsey Global Institute (2017). Reinventing Construction: A Route to Higher Productivity, McKinsey Global Institute.

3. Chandrasekaran, S. (2023, November 01). Capital Projects 5.0: Reimagining Capital Project Delivery. Available online: https://www.mckinsey.com/business-functions/operations/our-insights/capital-projects-50-reimagining-capital-project-delivery.

4. Ernst & Young (2014). Spotlight on Oil and Gas Megaprojects, Ernst & Young.

5. Dedasht, G., Zin, R.M., Ferwati, M.S., Abdullahi, M.M., Keyvanfar, A., and McCaffer, R. (2017). DEMATEL-ANP Risk Assessment in Oil and Gas Construction Projects. Sustainability, 9.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3