Abstract
The conventional energy source in cement industries is fossil fuels, mainly coal, which has a high environmental footprint. On average, energy expenditures account for 40% of the overall production costs per ton of cement. Reducing both the environmental impact and economic expenditure involves incorporating alternative energy sources (fuels) such as biomass, solid-derived fuel (SDF), refuse-derived fuel (RDF) etc. However, within cement plants, the substitution of conventional fossil fuels with alternative fuels poses several challenges due to the difficulty in incorporating additional fuel-saving techniques. Typically, an additional 3000 MJ of electricity per ton of clinker is required. One of the most effective solutions to this is thermal optimization through co-processing and pre-processing, which makes it possible to implement additional fossil-fuel-saving techniques. In developing nations such as Togo, waste-management systems rely on co-processing in cement factories through a waste-to-energy relationship. Also, there are some old cement plants with low-efficiency, multi-stage preheaters without pre-calciners, reciprocating huge coolers, low-efficiency motors etc., which still operate and need to be made environmentally sustainable. However, compared to modern kilns which can have up to 95% of energy recovery from waste, an old suspension preheater kiln can recover only up to 60% of its heat energy depending on the cooler type, and due to the lack of a bypass and combustion chamber (pre-calciner). This research paper evaluated the performance of a cement plant incorporating AF and presents the procedures and recommendations to optimize AF substitution in cement plants. To achieve this, a comparative performance study was carried out by assessing the alternative fuel characteristics and the equipment performance before and after the incorporation of the alternative fuel. Data were collected on the optimum substitution ratio, pre-processing and co-processing performance, raw-meal design and economic analysis. Results indicated that the cost to be covered per ton of waste input is €10.9 for solid-derived fuel (SDF), €15 for refuse-derived fuel (RDF), and that the co-processing cost optimization for the cement plant could have a cost saving of up to 7.81€/GJ. In conclusion, it is recommended that appropriate kiln and alternative-fuel models be created for forecasting production based on various AF.
Subject
Energy (miscellaneous),Energy Engineering and Power Technology,Renewable Energy, Sustainability and the Environment,Electrical and Electronic Engineering,Control and Optimization,Engineering (miscellaneous),Building and Construction
Reference95 articles.
1. Analysis of energy-efficiency opportunities for the cement industry in Shandong Province, China: A case study of 16 cement plants;Hasanbeigi;Energy,2010
2. Duda, J. (2004). Energooszczędne i Proekologiczne Techniki Wypalania Klinkieru Cementowego, Wydawnictwo Instytut Śląski.
3. Modernization and increase in capacity at Malogoszcz Cement plant;Duda;World Cem.,1996
4. Schwaiger, G. (2012). Chez Europe Cement Conference, Available online: https://www.researchgate.net/profile/Marek-Wasilewski-2/publication/259974245_Influence_construction_of_suspension_preheater_on_energy_consumption_process_during_burning_in_rotary_kiln/links/0046352ecd831546e1000000/Influence-construction-of-suspension-preheater-on-energy-consumption-process-during-burning-in-rotary-kiln.pdf.
5. Energieersparnis durch Umbau eines 4 stufigen Zyklonvorwärmers in einen 5 stufigen Wärmetauscher;Igawa;ZKG Int.,1986
Cited by
7 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献