Design Optimization Methodology for Diversion Structure with Concrete Cofferdam Using Risk-Based Least-Cost Design Method

Author:

Hong Wonpyo1,Eum Taesoo2ORCID,Song Chang Geun2

Affiliation:

1. DL E&C, Nepal UT1 HEPP Project Team, Seoul 03181, Republic of Korea

2. Department of Safety Engineering, Incheon National University, Incheon 22012, Republic of Korea

Abstract

The optimal size of a diversion structure should be carefully studied to ensure economic viability and safety during construction. In practice, to determine the size of a diversion structure, design flood frequency is selected as the suggested return period presented by the design standard, which is presented differently. This study proposes a methodology for the design of a diversion structure with a concrete cofferdam adopting risk analysis to reflect the more practical hazard and risk of diversion structure during dam construction. The proposed methodology is based on a risk-based least-cost design process and risk analysis. The optimization result is presented as the lowest expected monetary value, which accounts for construction cost, reconstruction cost, and delay liquidated damage with the failure probability and recovery cost with the overflow probability. This methodology was applied to the case study of the Gulpur hydropower project in Pakistan. The results showed that the optimal design flood frequency is 1 year for a recovery cost of USD 0.5 mil. and 1~2 years for a recovery cost of USD 1.0~2.0 mil. with 3, 4, and 5 years of the usage period of the diversion structure. Furthermore, 2~10 years is the optimal value for a recovery cost of USD 3.0~4.0 mil. These results indicated that the optimal design flood frequency increases as the recovery cost and usage period of the diversion structure increase. The results of the study reveal that the recovery cost and the period of use of the diversion structure affect the design flood frequency of the diversion structure. From a design perspective, the period of use is determined by the construction period of the project or the construction method, whereas the recovery cost depends on the countermeasure method. Therefore, after preparing a proactive plan and estimating the recovery cost, the design flood frequency for the diversion structure should be determined.

Funder

a Incheon National University Research

Publisher

MDPI AG

Subject

Fluid Flow and Transfer Processes,Computer Science Applications,Process Chemistry and Technology,General Engineering,Instrumentation,General Materials Science

Reference12 articles.

1. (1986). Bulletin 48a: River Control during Dam Construction, ICOLD (International Commission on Large Dams).

2. (2011). Dam Design Standard, KWRA (Korea Water Resources Association).

3. Tung, T.K., Yen, B.C., and Melching, C.S. (2006). Hydrosystems Engineering Reliability Assessments and Risk Analysis, McGraw-Hill.

4. Risk-based optimization of large flood-diversion systems using genetic algorithms;Afshar;J. Eng. Optim.,2009

5. Risk-Cost Optimization of Hydraulic Structures: Methodology and Case Study;Rasekh;J. Water Resour. Manag.,2010

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3