Study on the Mechanism of Safety Risk Propagation in Subway Construction Projects

Author:

Han Yuanwen12,Shen Jiang1,Zhu Xuwei3ORCID,An Bang1,Liu Fusheng1,Bao Xueying2

Affiliation:

1. Management Science and Engineering, Tianjin University, Tianjin 300072, China

2. College of Civil Engineering, Lanzhou Jiaotong University, Lanzhou 730070, China

3. Key Laboratory of Road and Traffic Engineering of the Ministry of Education, Tongji University, Shanghai 201804, China

Abstract

Under the development trend of complexity and systematization of metro construction, there is an increasing number of risk factors potentially affecting construction safety, which has led to frequent accidents in metro construction projects, and the road to high-quality and sustainable development of metro construction is full of challenges. One of the essential reasons is that the propagation mechanism of safety risk factors in metro construction under hidden and delayed effects is not yet clear. This paper combines the theory of complex network and propagation dynamics and constructs a subway construction safety risk propagation model based on considering the hidden and delayed characteristics of construction safety risk propagation, which reveals the dynamic propagation law of subway construction safety risk and puts forward feasible coping strategies. The findings evince that the delay time T significantly affects the propagation behavior of risk and the achievement of the equilibrium state in the network. The transmissibility of the risk factor within the hidden state holds a pivotal sway over the entirety of risk propagation, and the latency in transmission significantly expedites the propagation of risk throughout the network. It is recommended that project managers monitor and warn safety state nodes and hidden state nodes to block the spread of risk in the network and control the delay time of risk in the network in time to reduce the probability of risk occurrence. This study significantly promotes the resilient management of safety risks in metro construction.

Funder

National Natural Science Foundation of China

Publisher

MDPI AG

Subject

Management, Monitoring, Policy and Law,Renewable Energy, Sustainability and the Environment,Geography, Planning and Development,Building and Construction

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3