Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia

Author:

Melaku Belay Solomon1ORCID,Tilahun Seifu1,Yehualaw Mitiku1,Matos Jose2,Sousa Helder2ORCID,Workneh Endalew Temesgen3

Affiliation:

1. Faculty of Civil and Water Resource Engineering, Bahir Dar Institute of Technology, Bahir Dar, Ethiopia

2. Department of Civil Engineering, University of Minho, Guimaraes, Portugal

3. Construction Works Regulatory Authority, Addis Ababa, Ethiopia

Abstract

Today, several developing countries struggle to improve the cost and time performances of major infrastructure works due to various reasons. Cost overrun and delay are one of the major challenges being faced by the construction and infrastructure sector. Hence, the aim of this study is to explore the extent of cost overrun and schedule delays in building and road infrastructure projects across the Ethiopian construction industry. Primary data were collected through a structured questionnaire survey to evaluate the potential risks leading to those challenges. Various data analysis tools were employed, to investigate the critical causes of cost overrun and delays in infrastructure projects. The findings reveal that the minimum cost overrun for building construction projects is found to be 2%, whereas the maximum and average cost overruns are 248% and 35%, respectively. For road infrastructure projects, the minimum, maximum, and average cost overruns are found to be 1%, 61%, and 18%, respectively. Similarly, the minimum, maximum, and average delays recorded in building construction projects are 9%, 802%, and 143%, respectively, whereas, in road infrastructure projects, the minimum delay is found to be 3%, the maximum delay is 312%, and an average schedule delay of 110% is recorded. In addition, the top risk factors leading to cost overrun in infrastructure projects are inflation, inaccurate cost estimates, and variations, whereas the major risks causing schedule delays are variations, economic conditions, and escalation of material prices. Further, practical implications and key recommendations were provided to curb cost overrun and delay in infrastructure projects.

Funder

Construction Works Regulatory Authority of Ethiopia

Publisher

Hindawi Limited

Subject

Civil and Structural Engineering

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3