Study of Deformation Behaviors and Mechanical Properties of Central Diaphragm in a Large-Span Loess Tunnel by the Upper Bench CD Method

Author:

Luo Yanbin1ORCID,Shi Zhou1ORCID,Chen Jianxun1ORCID,Liu Weiwei1ORCID,Li Yao1,Wu Yunfei1,Zhu Haoyang1

Affiliation:

1. School of Highway, Chang’an University, Shaanxi, Xi’an 710064, China

Abstract

The central diaphragm is often used to reduce the span to maintain the stability and safety of structure in the construction of large-span loess tunnel due to the structure complexities. In this paper, relying on the field monitoring and measurement for Wangcun tunnel in Huangling-Yan’an expressway expansion project, the crown settlement and horizontal convergence of primary support steel rib and central diaphragm steel rib during the construction are analyzed by the upper bench CD method. According to the internal force transfer, deformation coordination, and arch foot displacement between the two structures, the support system is regarded as the arch-beam fixed structure with three times of statically indeterminate and movable abutment under the loads, and the mechanical calculation model of sidewall steel rib and the central diaphragm structure bearing loads and deformation together is established. Finally, through the mechanical model mentioned above, the deformation characteristics of central diaphragm structure and the horizontal convergence in the upper bench of tunnel are calculated and analyzed. The research shows the following: (1) the accumulated settlement of sidewall steel rib in Part I is greater than that of the sidewall steel rib in Part II, and the accumulated settlement of each part at the support structure during the tunnel excavation is less than the reserved deformation of 150 mm specified in the tunnel excavation; (2) the settlement located at the waist and maximum excavation line position of central diaphragm is mainly affected by the excavation of Parts I and II in upper bench; (3) during the whole excavation process, the excavation of Part I and Part II has the greatest influence on the convergence at arch waist and the maximum excavation line position in Part I, and the convergence at the above two positions all experienced four stages of “convergence-expansion-convergence-gradual stability”; and (4) the errors between the horizontal convergence and the deformation of central diaphragm obtained by the mechanical model and the field monitoring data are between 12.7% and 27.5%. The calculated results are in good agreement with the actual situation. The research can provide a theoretical basis for the study of deformation and mechanical properties for support structure in the construction of large-span loess tunnel by the upper bench CD method.

Funder

National Key R&D Program of China

Publisher

Hindawi Limited

Subject

Civil and Structural Engineering

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3