Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

Author:

Berihu Lielti Gebreegziabher1,Grum Berhane1ORCID,Tariku Zeru1,Abebe Bizuneh Asfaw1ORCID

Affiliation:

1. School of Civil Engineering, Ethiopian Institute of Technology-Mekelle, Mekelle University, P.O. Box 231, Mekelle, Ethiopia

Abstract

Project cost overrun and schedule delay are major and widespread problems in the construction industry. In Tigrai, most water supply construction projects are not completed within the predetermined contract time and planned budget. Hence, this research was carried out to investigate the causes and effects of time and cost overrun in water supply projects in Tigrai, northern Ethiopia and further recommend effective mitigation measures. A total of 87 questionnaires were distributed, 50 of them were collected, and desk study of 12 water supply projects were conducted. Data were analyzed using relative importance index and statistical software SPSS version 20. Results showed that the most important causes of time overrun were design errors and changes, lack of consistency between bill of quantities and drawings, and change order. Similarly, the most important causes of cost overrun were design errors and changes, lack of consistency between bill of quantities and drawings, and shortage of construction materials and electromechanical equipment in local market. The most effective mitigation measure of the overruns was complete and proper design. Time and cost overrun of the projects ranged between 0 and 203% and between 0 and 25%, respectively. The regression model showed that time overrun was estimated well (r2 = 0.95) using delays caused by design errors and changes and material import. Similarly, cost overrun was estimated well (r2 = 0.98) using factors that affect cost. Overall, the major cause for the overruns was design problem, hence clients and consultants should give due attention for the design process.

Funder

Mekelle University-Norwegian University of Life Sciences

Publisher

Hindawi Limited

Subject

Civil and Structural Engineering

Reference37 articles.

1. Preliminary study on causative factors leading to construction cost overrun;A. H. Memon;International Journal of Sustainable Construction Engineering and Technology,2011

2. How common and how large are cost overruns in transport infrastructure projects?

3. Should we build more large dams? The actual costs of hydropower megaproject development

4. An Analysis of Cost Overruns and Time Overruns of Construction Projects in India

5. Causes and effects of cost overrun on construction projects in Madhya Pradesh;S. K. Prajapati;International Journal of Experimental Diabetes Research,2016

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3