Track alignment on crushed ballast with installation of under sleeper pads and pneumatic shovel packing

Author:

Pevzner V. O.1,Kaplin V. N.1,Abrashitov A. N.2,Semak A. V.2

Affiliation:

1. Joint Stock Company “Railway Research Institute” (JSC “VNIIZhT”)

2. Federal State Budget Educational Institution of Higher Education “Russian University of Transport” (FGBOU VO RUT (MIIT)

Abstract

Specialists of the Scientific Research Institute of Railway Transport (JSC “VNIIZhT”) and Tracks and track facilities Department of the RUT (MIIT) initiated the procedure in consultation with the Test Center of the JSC “VNIIZhT”, tests were performed on the Test Loop of the JSC “VNIIZhT” in Shcherbinka. The experiment was carried out to confirm the possibility of straightening the track in the profile by instal ling under-slipper pads and pneumatic shovel packing (by padding with the use of a compressed air stream to transfer and distribute the fine gravel particles under the sleeper). The purpose of the test was to search for alternative ways for piling up crushed ballast. As a result of the experiment, it was established:the use of pads and pneumatic shovel packing provides a much greater stability of the track in the profile than the alignment of the track by padding the ballast under the sleepers with electric packing machine;pneumatic shovel packing creates a greater resistance to the sleeper creeping in the zone of the mechanical joint in comparison with the adjustment of punching rubble for sleepers with electric packing machine with identical fasteners (the experimental and control joints follow one another);alignment with the installation of pads and pneumatic shovel packing can be successfully applied on the railway track with a large missed tonnage and high pollution of the ballast prism. The results of the tests carried out on the Test Loop of the JSC “VNIIZhT” help to refine the advanced technologies for straighte ning the railway track in the profile to under-sleeper pads and pneumatic shovel packing for the future creation of experimental sections on the existing rail track and the possible extension of these ways of straightening the railway track in the profile to the entire network.

Publisher

JSC Vniizht

Reference9 articles.

1. Abrashitov A. Experimental study of stoneblowing track surfacing technique. Proceedings of Transportation Geotechnics and Geotechnology (TGG-2017), St. Petersburg, 17 – 19 May 2017. St. Petersburg, 2017. Vol. 189, pp. 75 – 79.

2. Waters J. M. Pneumatic stone injection a means of adjusting track level. Fourth International Rail Track & Sleeper Conference. Adelaide, 1981, pp. 1 – 14.

3. Pevzner V. O., Zheleznov M. M., Kaplin V. N., Tret'yakov V. V., Myslivets M. N., Tomilenko A. S. Povyshenie stabil'nosti puti v zone stykov za schet primeneniya uprugikh podshpal'nykh prokladok [Increasing track stability in the zone of joints due to the use of elastic under sleeper pads]. Vestnik VNIIZhT [Vestnik of the Railway Research Institute], 2016, Vol. 75, no. 3, pp. 140 – 146. DOI: http://dx.doi.org/10.21780/2223-9731-2016-75-3-140-146.

4. Anderson W. F. Experiences with the stoneblower on the UK. Proceedings of the international conference railway engineering (London, UK, July 2002). London, Engineering Technics Press, 2002. CD-ROM.

5. Technically valid standard time for work on the current maintenance of way. Approved by the JSC “Russian Railways” dated 30.03.2009, revised as of 05.08.2015, 7th edition in 2 parts. Moscow, 2015 (in Russ.).

Cited by 3 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3