Managing material shortages in project supply chains: Inventories, time buffers, and supplier flexibility

Author:

Kouvelis Panos1ORCID,Chen Xingxing2ORCID,Xia Yu3ORCID

Affiliation:

1. Olin Business School, Washington University in St. Louis, St. Louis, Missouri, USA

2. Robins School of Business, University of Richmond, Richmond, Virginia, USA

3. Mason School of Business, The College of William & Mary, Williamsburg, Virginia, USA

Abstract

We consider a two‐stage project supply chain with a downstream project firm producing an engineer‐to‐order (ETO) complex product or a make‐to‐order (MTO), low‐volume, customized industrial product as a project, and an upstream contract supplier supplying a key material to the project. The project faces two uncertainties: project activity time uncertainty and material consumption uncertainty, which may be positively or negatively correlated. In anticipation of these uncertainties, the project firm has to carefully decide its promised project due date to its project customer, against which harsh penalties will be assessed, and his material order quantity to commit to the contract supplier in advance. In most practical settings, project firms order from contracted suppliers via a flexible wholesale price contract consisting of a discounted advance order price and a risk‐premium adjusted expedite order price. The discounted advance order price encourages the project firm to take more inventory risk in the supply chain, and the expedite order price incentivizes the supplier to bear more inventory risk by carrying safety stock in excess of the project firm's advance material order. We formulate an optimization model that solves the project firm's project due date and material order problem, which takes into account the supplier's strategic reaction to the project firm's material order under the flexible wholesale price contract. We show that for MTO projects, risk‐sharing with suppliers on project materials is less important to the project firm, with the project firm assuming ownership of all material inventory in the channel and setting a deliberate project due date being the key. On the other hand, for ETO projects, risk‐sharing with contracted suppliers assumes critical importance. Project firms managing ETO projects should fully exploit the flexibility in the material supply contract to optimally drive the supplier's safety stock level and set the project due date reflecting the shared risk in the supply chain.

Publisher

SAGE Publications

Subject

Management of Technology and Innovation,Industrial and Manufacturing Engineering,Management Science and Operations Research

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. The impact of delayed fixed-price payment in the decentralised project supply chain;International Journal of Systems Science: Operations & Logistics;2024-02-05

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3