Case Study: First Successful Offshore ESP Project in Saudi Arabia

Author:

Al Zahrani Ahmed R.1,Al-Nasser Redha H.1,Collen Timothy W.1,Khade Sudhakar2

Affiliation:

1. Saudi Aramco

2. Schlumberger

Abstract

Abstract The Electrical Submersible Pump (ESP), a form of artificial lift technology, has proven to be a durable solution for delivering the required rates from Saudi Aramco fields. Therefore, this form of artificial lift was selected to increase production rate from one of the offshore fields, while optimizing offshore producing facilities. This offshore field has favourable conditions for ESP application, producing from carbonate reservoir with no anticipated fines production, low GOR, low temperature, low bubble point pressure and high API gravity. All new installations were carried out without interrupting the ongoing production target. The project has completed a four-years operating cycle while continuously maintaining the field production rate with an acceptable ESP failure and run life. So far, 41% of the originally installed ESP systems are operating more than 4 years and 20% are operating in the range of 3–4 years run life. The cumulative average run life of operating ESPs is 2.7 years and that of failed ESPs is 1.74 years. To maintain required production target, an effective ESP replacement program is a core element of field production strategy. Therefore, several measures such as replacement of underperforming ESP systems and upsizing of the pumps have been implemented. Furthermore, Dismantle Inspection and Failure Analysis (DIFA) of pulled ESP systems were conducted to evaluate the root cause of the failures and remedial actions were implemented to prevent such occurrences in future. Increasing Motor Lead Extension cable thickness, utilization of tandem seals and new wellhead penetrators are also expected to further enhance the ESP run life. New applications to minimize ESP failures due to human intervention and ensure proper equipment handling during installations are being pursed. In addition, tandem ESP completions and different types of wellhead penetrators are being pursued to reduce rig utilization, increase producing life and minimize failures. Introduction Saudi Aramco discovered the offshore field in 1963 and placed it in natural production from 1966 until 2004. The primary reservoir is hydraulically supported by natural water influx. The field produces Arabian Medium crude with an average oil gravity of 30° API and 2.7% sulfur by weight.

Publisher

SPE

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Feasibility study formulation for the applicability of rigless temporary ESPs;Journal of Petroleum Exploration and Production Technology;2022-04-20

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3