Affiliation:
1. Blade Energy Partners, Frisco, Texas, USA
Abstract
Abstract
This work discusses the experience and results of generating a rig-specific riser gas handling (RGH) procedure based on previous project experiences and the IADC Riser Gas Handling Guidelines developed by the Riser Gas Handling sub-committee of the IADC Underbalanced Operations and Managed Pressure Drilling Committee. In this work the authors differentiate between what should be considered RGH, and what should be considered dynamic influx management, and define the boundaries between both processes.
It presents an example procedure under the following premises as main indicators to identify and differentiate the gas in the riser, for example a) high concentration of gas in the mud was detected in the shakers, b) gas units and LEL setting level, c) Undetected influx producing gas expansion in the riser increasing flow out. The presentation includes a brief discussion on the theory involved, preparation required, and responsibilities, and provides an example procedure and process flow diagram.
Reference4 articles.
1. API RECOMMENDED PRACTICE 92S Managed Pressure Drilling Operations—Surface Back-pressure with a Subsea Blowout Preventer;American Petroleum Institute,2018
2. Gabaldon, Oscar, Gonzalez, Romar A., Bacon, William, and PatrickBrand. "Influx Management Envelope: Limits Redefinition and Parametric Sensitivity Analysis Based on Data and Lessons Learned from Offshore Applications." Paper presented at the IADC/SPE Managed Pressure Drilling and Underbalanced Operations Conference and Exhibition, Amsterdam, The Netherlands, April 2019. doi: https://doi.org/10.2118/194537-MS
3. Drilling Manual 12th Ed. - Riser Gas Handling Guidelines Chapter;IADC,2023
4. Mud/Gas Separator Sizing and Evaluation;MacDougall;SPE Drill Eng,1991