Valhall Field - Still on Plateau after 20 Years of Production

Author:

Barkved Olav1,Heavey Pete1,Kjelstadli Roar1,Kleppan Tore1,Kristiansen Tron Golder1

Affiliation:

1. BP

Abstract

Abstract The estimated recoverable reserves from the Valhall field at start of production in 1982 were 250 MMSTB. Now, after twenty years on primary depletion, a total of 500 MMSTB has been produced and additional 500 MMSTB remains to be produced of the original 2.6 BSTB in place. This corresponds to a recovery factor of 40%. Possibilities to increase ultimate recovery have been defined. These will require further insights into the detailed architecture of the field and improved understanding of the reservoir energy and displacement efficiency. Approximately 50% of the drive to date has been from rock compaction. The field is a North Sea Chalk field producing from Tor and Lower Hod Formations, porosity is exceeding 50% in places, some fractured permeability is present, but matrix permeability is generally low, less than 10 mD. Application of new technology has been fundamental in bringing the field up to current performance. New completion techniques combined with dedicated draw down schedules has been established to reduce influx of the weak chalk formations and reduce well failures. Special well design for a compacting and subsiding environment has also been implemented. Drilling of the overburden has been a key challenge. This has been partly mitigated by detailed geological mapping of problem zones versus structure, lithology, overpressure and wellbore stability analysis, but has also resulted in replacing extended reach wells by the installation of new flank drilling and production facilities. The particular characteristics of the overburden and chalk also pose challenges for data acquisition. Coring technology & practices are very tightly controlled, as is selection of logging devices. A water flood scheme has been approved based on a successful water flood pilot, but issues related to sweep efficiency, presence of fault and fracture zones and large variation in thickness need to be understood to capture it's full potential. The reservoir will also experience extra water induced compaction and increased subsidence. New logging technology has recently made it possible to define and characterize the fracture system, which combined with a range of surveillance techniques will be key in this work. Seismic imaging has generally been a challenge at Valhall due to the presence of gas in the overburden. Use of 4C seismic technology has improved this. In addition, the 4D seismic response appears to be very sensitive to production-induced depletion, compaction of the reservoir and subsidence of the overburden and seafloor. Seismic techniques will be critical in future development. For a more detailed review of the first 10 years of Valhall, reference is made to the paper by Ali and Alcock [1]. Field History The Valhall field is an over-pressured, under-saturated Upper Cretaceous chalk reservoir located in the North Sea approximately 290 km offshore southern Norway in 69 m of water. The field is located in the most southwestern corner of the Norwegian continental shelf, Figure 1. The Valhall field was discovered in 1975, after exploration drilling in the period 1969 - 1974. Decision to develop the field was made in 1978 and the field started producing in October 1982. During appraisal drilling the first issues with soft chalk and solids production were experienced. Although early core tests indicated a high compaction potential, it was believed that the relatively thin chalk section would not result in significant subsidence. The platforms, however, were built tall enough to withstand some subsidence. The initial development consisted of a 3-platform complex (quarters platform, drilling platform and process/compression platform). Later, in 1996, a fourth platform was added (wellhead platform) to provide additional slots for infill drilling. In 2000, the Valhall partnership approved a water injection program, from an additional Injection platform, IP. With continued subsidence, drilling wells in the overburden became increasingly difficult. To provide efficient access to the flank areas in the North and South, installation of two new wellhead platforms was approved in 2001.

Publisher

SPE

Cited by 34 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3