A Probabilistic Approach for Drilling Cost Engineering and Management

Author:

Saibi Mohamed1

Affiliation:

1. Sonatrach

Abstract

Abstract One of the major challenges facing drilling operations engineering and management today is the prevention of costs and schedule overruns. The nature of drilling operations with the diversity of parties involved in the different tasks from well conception up to the completion, the more and more sophisticated technology used, the pressure of time, the increasing regulatory of safety and environment requirements, the inflating costs in addition to the big uncertainty of this activity make difficult meeting the financial and timing targets set for the premeditated financial resource allocation. The first objective of this paper is to provide the drilling manager with an efficient cost management and control tool that facilitates the management of the expenditures, and enables to take informed decision and corrective actions on the right time, by providing better understanding and awareness of the actual exposure to the cost overrun risks. Cost control techniques can be adapted to the well construction process by using the information gathered from the offset wells to mitigate the effect of the uncertainty of nature. Many studies have been made on this issue; they can be classified into deterministic and probabilistic approaches. For the latest, little work has been carried out and it is still not widely and comprehensively used in practice in spite of its powerfulness. The methodology used in this study consists, firstly, of analyzing data from offset wells to simulate and reproduce real life scenarios of possible cost outcomes based on Monte Carlo simulation combined with risk analysis to be applied in the planning phase of new wells, and secondly, of applying a real time control and continuous improvement processes in the execution phase. This paper illustrates the case study of Hassi-Messaoud oilfield in Algeria. This type of model facilitates the management tasks and save time and efforts, particularly when dealing with intensive drilling operations in major fields. Introduction Intensive drilling operations are carried out in today's oil and gas major fields, which require careful planning and precise implementation, especially as far as drilling costs are concerned that are critical to the overall economic performance. To achieve a high quality cost management, we need to answer the following questions: first, how to prevent cost overruns? How to assess uncertainty? How to manage costs for the aim of informed decisions and corrective actions? To which reference does a drilling team set a cost target? And how to calculate performance in terms of cost? To be able to face those difficulties the drilling manager needs an efficient tool that enables the control of expenditures and schedule in the frame of the requirements of quality and safety. This tool will help the drilling manager to: Know what have to be done (the estimation), know what have been done (progress), know what is left to be done (previsions), consider the possible cost overruns, control the expenses, in real time, and their projection at the end of the project, and finally, use the lessons learnt to improve the performance. First of all, the quality of planning is very important to achieve a successful cost management of the drilling project because it contains two keys to drill a cost effective well: minimizing problems and maximizing progress, therefore properly written drilling program leads to a cheaper well [1]. An important step in the planning process is the well cost estimation, which represents an integral part of the AFE [2] (authorization for expenditures) procedure that is mainly a tool for controlling expenditures. Therefore, the AFE should be written to ensure that just enough money has been approved to drill the well without being short of funds, or leaving unspent funds on the table [1], for the aim of an optimal financial resources allocation. Because uncertainty is ever present when dealing with nature, probabilistic approach is the suitable way to count for inherent risks in the process of well cost estimation and management [3]. The estimate enables to define the productivity team targets to be used for detailed control.

Publisher

SPE

Cited by 3 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Machine Learning Vs. Statistical Models Approach: A Case for Probabilistic AFE Cost in Drilling;Day 3 Wed, November 02, 2022;2022-10-31

2. The Precise Estimation of Development Project Cost and its Life Cycle;Vestnik of the Plekhanov Russian University of Economics;2021-12-22

3. Probabilistic Drilling Time Estimation Using Monte Carlo Simulation;Journal of the Korean Society of Mineral and Energy Resources Engineers;2018-06-01

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3