Merging Tapered in Coiled Tubing (CT) and Well Tractor Technologies to Effectively Stimulate Extended Reach Open Hole Horizontal Wells

Author:

AlDhufairi Mubarak1,AlGhamdi Saleh1,Noya Vidal2,Al-Aradi Khaled2,Al-Sarakbi Samer2,Al-Dossary Ahmed2,Krueger E..3,Moore B..3

Affiliation:

1. Saudi Aramco

2. Schlumberger

3. WWT

Abstract

Abstract The M field development involves one of the largest drilling projects in Saudi Arabia, targeting various carbonate reservoirs, and with an extraordinary amount of extended reach wells (ERWs) requires meeting the expected oil production rate, at the lowest development cost possible. More than two-thirds of the wells fall under the extended reach drilling classification, and the majority of the wells have measured depths (MDs) between 24,000 ft and 31,000 ft. These wells are open hole completions where acid stimulation is highly needed to overcome reservoir damage and improve the well's performance after drilling operations terminate. The placement of the treatment fluids requires a uniform distribution along the open hole section. Among the different techniques considered, namely bullheading, using the rig drill pipe and coiled tubing (CT), the last one offered the soundest technical and cost option. However, the CT technique alone did not show the ability in reaching the maximum depth in most ERWs of this field. Therefore, the tractor1 was required to provide the significant amount of pull force needed to operate inside these long distances, not seen before in open hole completions. The first eight well campaigns, using a combination of CT, a hydraulic tractor and friction reducer fluids, have achieved the main objectives. Moreover, a new intervention world record2 was set when the CT bottom-hole assembly (BHA) reached the maximum depth of 28,257 ft inside open hole in two different occasions, to place the stimulation fluids, and to record an injection profile. During the campaign, a total of 41,774 ft accumulated footage has been operated with the tractor, allowing over 3,400 bbls of acid to be placed in direct contact with the formation. As a result, the average injection rate has increased more than tenfold, reducing the drilling requirements for injection wells originally projected. The job preparation, technology, results, learning curve experience and best practices are discussed in this paper, including proposed operational enhancements. This experience demonstrates the feasibility of the operations with CT required for full zone coverage, yielding optimum water injection rates at the lowest development cost.

Publisher

SPE

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Buckling-induced lock-up of a slender rod injected into a horizontal cylinder;International Journal of Solids and Structures;2015-10

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3