Development of technology for additional extraction of potash ore reserves from previously mined out panels at the depths exceeding 600 metres of the Starobin potash salt deposit

Author:

Golovaty I. I.1,Chizhik S. A.2,Petrovskiy A. B.1,Prushak V. Ya.3

Affiliation:

1. JSC “Belaruskali”

2. Presidium of the National Academy of Sciences of the Republic of Belarus

3. Soligorsk Institute of Resource Saving Problems with Pilot Production

Abstract

Studied the possibility to extend the life of the Production Unit no. 3 mine of JSC “Belaruskali” through the additional extraction of sylvinite ore reserves left in the previously mined panels of the mine field of the 3rd potash level. It was determined, that during the period from 1971 to 1980 a considerable part of the southern direction of the mine field on the area of more than 5,3 million m2 was mined by the roadways on the layers 2, 2–3, 3 without the mining of the 4th sylvinite layer. The volume of the leftover reserves of minerals in the mined panels makes more than 22 million tons. There is direct access to these panels from the main southern gates. As a study result of geological structure of the mined panels it was determined that under the influence of rock pressure the undermined sylvinite layer no. 4 took the form of a wave-shaped seam with the capacity of about 1 meter which rests on compressed inter-chamber pillars and on compressed rocks of layers 2, 2–3, 3 of destroyed inter-roadway pillars, which fills the space of the roadways. Such geological structure of the seam enables to extract minerals using the technology of selective layer mining by successive top and bottom faces. As a study result of the stability of the mine workings performed along the roadways and inter-chamber pillars under conditions of different roof positioning, it was determined that during the preparation of the faces the most advantageous locations for development workings are the areas previously mined by the room and pillar mining system. In this case, the highest stability of mine workings located in the stopes of the room and pillar mining system will be provided by their roofing location with cut of 0.15 m of the 4th sylvinite layer. When this occurs, their predicted life without repair, even without the use of special protection methods, would be between 3.5 and 8 years. Based on the results of the study, a conclusion was made on the technical possibility and economic feasibility of additional extraction of sylvinite ore reserves left in the western panels of the southern direction of the mine field of the 3rd potash level of the Production Unit no. 3 mine, finished over 40 years ago by the room and pillar mining system using selective layer mining technology by the longwall faces. With minimal capital, organizational and technical expenditures, the extraction of these reserves will allow the company to produce additionally 5.5 million tons of potash fertilizers.

Publisher

Publishing House Belorusskaya Nauka

Subject

Pharmacology (medical)

Reference9 articles.

1. Zubov V. P., Smychnik A. D., Kirienko V.M. Enhancement of the development system of the 3rd potash seam at the mines of PA “Belaruskali”. Zapiski Gornogo instituta = Journal of Mining Institute, 2006, vol. 168, no. 3, pp. 15–18 (in Russian).

2. Podlesnyi I. A., Getmanov V. N., Petrovskii B. I., Nosulya I. E. Technology of the layer mining while developing the 3rd potash level of the Starobin deposit. Gornyi zhurnal = Mining Journal, 2018, no. 8, pp. 59–64 (in Russian). https://doi.org/10.17580/gzh.2018.08.08

3. Polyakov A. L. Analysis of the geological structure of the roof of the 3rd potash layer at the Starobin potash deposit. Gornaya mekhanika [Mining Mechanics], 2002, no. 2, pp. 30–36 (in Russian).

4. Puzanov D. A., Mozgovenko M. S., Gubanov V.A. Study results on the stability of mine openings when they are driven in the 4thsylvinite layer, undermined by the bottom face, PU 3 mine, JSC Belaruskali. Gornaya mekhanika i mashinostroenie [Mining Mechanics and Mechanical Engineering], 2014, no. 1, pp. 26–34 (in Russian).

5. Gubanov V. A., Puzanov D. A., Mozgovenko M. S., Erokhin K. A., Podlesny I. A., Petrovsky A. B., Dolgikh A. S. Study of manifestations of rock pressure in development and stope workings during mining the underworked and left reserves in the 4thsylvinite layer and inter-stope pillar by the test face No. 11-3 of the level – 620 m, PU 3 mine, JSC Belaruskali. Gornaya mekhanika i mashinostroenie [Mining Mechanics and Mechanical Engineering], 2017, no. 2, pp. 5–18 (in Russian).

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3