Electrical Protection From Design to Commissioning for Subsea Electrically Heat Traced Flowline Pipe in Pipe System, The Challenge of Inaccessible Subsea Electrical Assets.

Author:

Minier Yves1,Silcock Donald Maclaren1

Affiliation:

1. Subsea7

Abstract

Abstract This paper will describe the analysis, optimisation and subsequent implementation of an electrical protection system utilised on a subsea Electrically Heat-Traced Flowline system (EHTF) using conventional topsides power protection equipment deployed in a novel topology. It will also discuss the project-imposed challenge of protecting an electrical subsea system of significant length from only a single feeder protection whilst keeping it simple, sensitive, rapid, and covering 100% of the long heating cable length. The paper will describe the detailed electrical analysis methods deployed, the additional electrical verification carried out and the decision-making processes and drivers choice used during an electrical system design optimisation challenge that was conducted in a short timeframe and planned around operational assets. The close collaboration between contractor, client, vendors and third-party expertise was fundamental to solve successfully the challenges and mitigate the overall risks. Key engineering processes described: Subsea Umbilical Riser and Flowline (SURF)/Topside interface management / interface meetings, design review process, use of interim design reviews, the decision scoring matrix, the go/no go risk assessments, pre-commissioning, commissioning, performance test. The benefits and drawbacks of the different electrical topologies investigated will be reported, specifically the retention of an isolated neutral system. The paper will provide the final chosen protection topology and the results of the individual component testing. A key observation to report being that when technology is new, the need to validate the implementation of it must be included in the initial design. There must be added monitoring even if it’s not thought to be essential at start of a project, even if it’s considered as "sugar coating" a design or adding complexity, there can be huge benefits on new technology deployment. The paper will report on the observed benefits of site integration testing versus individual routine / factory acceptance testing when deploying TRL7 items in novel topologies. The final commissioning results will be reported and an engineer’s view of a journey from concept to final commissioning will be presented. Existing literature is limited on electrical topology on subsea infrastructures and thus this paper enhances the industry knowledge base. The paper describes a novel topside protection system for subsea ground isolated loads. As the subsea industry turns towards electrification, it is essential that lessons are learned. This ensures novel solutions can be deployed provided a correct design verification process. The paper could trigger discussions around a new best practice recommendation about the interface topsides/subsea electrical infrastructures.

Publisher

OTC

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3