Subsea Compression – Åsgard Subsea Commissioning, Start-Up and Operational Experiences

Author:

Time N. P.1,Torpe H.1

Affiliation:

1. Statoil

Abstract

The Åsgard Subsea Compression (ÅSC) project has since project sanction in 2011 engineered, constructed, installed and commissioned the world's first Subsea Compression Station (SCSt). The ÅSC SCSt includes two individual compressor trains, each containing an 11.5 MW centrifugal compressor module, condensate pump module, scrubber module and inlet- and discharge cooler modules. The compressor trains are installed at a water depth of 260 meters, in a shared subsea structure with a total weight of 5100 metric tons, a footprint of more than 3300 m2, and height of 17 meters above the seabed. The SCSt is connected to a subsea manifold station routing all flow from the wells via the compressor trains to the gas processing platform Åsgard B. The installation includes a comprehensive SURF scope with more than 60 km of new flow lines, 11 PLEMs and 50 tie-in points. The compressor station is powered from the Åsgard A FPSO where a separate high voltage power module weighing 850 metric tons has been installed. The subsea station is remotely operated from the Åsgard B platform. The subsea compression station is compressing the gas flow from the Midgard and Mikkel reservoirs, boosting the production and securing stable flow conditions in the subsea flow lines towards Åsgard B. The subsea commissioning has been carried out during summer, autumn and winter 2015/2016. It has involved control system commissioning, dynamic commissioning with N2 and MEG, before final commissioning with hydrocarbons. In order to secure efficient commissioning with involvement of a large number of vendors and support personnel, a remote operation room for the commissioning team was installed at Statoil's Stjørdal office outside Trondheim where the Åsgard Operations land organization is housed, thus avoiding constraints imposed by offshore training, helicopter travel and shortage of offshore cabins. This paper describes the subsea commissioning phase, including experiences and lessons learned. Challenges including cooperation between onshore room, offshore platform, and installation vessel, as well as performing commissioning on one train with the other in operation, are discussed. In addition, it gives an outline of the experiences gained during the start-up and initial operation phases.

Publisher

OTC

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3