Significant factors affecting the Vietnam Roads Infrastructure Construction Cost Overrun - A Review

Author:

Hung Huu Nguyen 1,Tuan Anh Nguyen 2,Thien Chi Nguyen 3

Affiliation:

1. DEOCA Group, Vietnam

2. Ho Chi Minh City University of Transport, Ho Chi Minh City, Vietnam

3. The SDCT Group Research, Ho Chi Minh City University of Transport, Vietnam

Abstract

Cost overrun represents a significant challenge faced in construction projects, particularly in the realm of transportation infrastructure. The investigation into the causes of cost overruns in such projects has garnered substantial attention from both academics and the general public. Various studies conducted globally have identified diverse factors contributing to cost overruns. This article undertakes a critical review of the literature on cost overruns in construction projects, encompassing cases from different countries with a specific focus on Vietnam. The aim is to identify and comprehend the primary potential causes of cost overruns in construction projects across various geographical contexts, providing insights into both commonalities and distinctions within the identified factors. According to the findings of this study, the ten identified factors encompassing Delay in site clearance certificates, Change Management, Delay in Payment, Extension of the project implementation schedule, Construction Material Price Fluctuation, Effects of inflation and price slippage, Poor construction site management, Poor project management capacity of the investor, Poor financial capacity of the investor, Geological complexity are deemed highly influential and warrant close scrutiny during the implementation of projects in Vietnam. The insights gained from this study will serve as invaluable recommendations for active entities within the construction industry to adopt a more holistic approach to project management, cost control, and cost overrun management. By addressing quantitatively these factors in the forthcoming research, organizations in construction industries in Vietnam can effectively minimize project costs overrun in the future.

Publisher

Technoscience Academy

Reference20 articles.

1. Vietnamnet Global Magazine, 2023. https://vietnamnet.vn/en/vietnam-takes-action-to-build-3-000km-of-highway-by-2025-2157189.html

2. Vneconomy Magazine, 2022. https://vneconomy.vn/chon-duoc-nha-thau-manh-cao-toc-bac-nam-giai-doan-2-ky-vong-can-dich.htm

3. Long Le-Hoai, Young Dai Lee, and Jun Yong Lee. Delay and cost overruns in Vietnam large construction projects: a comparison with other selected countries. KSCE Journal of Civil Engineering, 2008, vol. 12, no.6, 367 – 377.

4. Tai Le-Huu, Thong Tran-Van, and Thuat Dang-Cong. Investigating factors affecting Construction Cost and Schedule Overruns of public investment projects. The Builder Magazine, 2022, no.3-4, 54-60.

5. Van, L. T., Nghia, N. H., & Khuong, L. T. (2012). Identifying Key Factors influencing cost variation of construction projects in Ho Chi Minh City. Ho Chi Minh city open University Journal of Science-Engineering and Technology, 2(1), 3-10.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3