MULTIOBJECTIVE OPTIMIZATION MODEL FOR SCHEDULING OF CONSTRUCTION PROJECTS UNDER EXTREME WEATHER

Author:

SENOUCI Ahmed B.1,MUBARAK Saleh A.1

Affiliation:

1. Qatar University

Abstract

Extreme weather significantly impacts construction schedules and costs and can be a source of schedule de­lays and budget overruns. A multi-objective optimization model, presented herein for the scheduling of construction projects under extreme weather conditions, can generate optimal/near optimal schedules that minimize the time and cost of construction projects in extreme weather regions. The model computations are organized as follows: (1) a scheduling module for developing practical schedules for construction projects, (2) a cost module for computing total project cost, and (3) a multi-objective module for determining optimal/near optimal trade-offs between project time and cost. Two practical examples of the effects of extreme weather on construction time and direct cost are provided, the first of which shows the impact of extreme weather on construction time and cost, and the second of which demonstrates the ability of the model to generate and visually present the optimal trade-offs between the duration and costs of construction projects under extreme weather conditions.

Publisher

Vilnius Gediminas Technical University

Subject

Strategy and Management,Civil and Structural Engineering

Reference27 articles.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3