JUSTIFICATION OF HYDROPOWER POTENTIAL OF THE VOVCHA RIVER FOR CONSTRUCTION OF SMALL HPP IN THE SITE OF GAVRYLIVKA RESERVOIR

Author:

Kovalenko V.1ORCID,Hapich H.1ORCID,Zaporozhchenko V.1ORCID,Shynkarenko I.1ORCID,Chushkina I.1ORCID,Dovhanenko D.2ORCID

Affiliation:

1. Dnipro State Agrarian and Economic University

2. Oles Honchar Dnipro National University

Abstract

The article presents the research results of the hydropower potential of the Vovcha River in the site of Gavrilivka Reservoir for construction of a small hydropower plant. During the research, statistical methods were used to analyze the homogeneity of long-term fluctuations of river flow. Estimation of parameters of analytical distribution curves (average long-term value Q, coefficient of variation СV, ratio of asymmetry coefficient to variation coefficient CS/CV) was performed by the maximum likelihood method. Determination of the estimated annual distribution of the flow in the site is carried out by the real year method. Methods for calculating the hydropower potential are based on the results of hydrological investigation. To achieve stated objective, the following tasks are solved: 1) the water resources of the Vovcha River in the Gavrilivka Reservoir were quantified; 2) the hydropower potential of the Gavrilivka Reservoir is estimated according to model years; 3) the value of technically achievable, guaranteed and ecologically justified hydropower potential is established; 4) technical and economic indicators of project practicability are assessed. The provision of HPP capacity has been determined both for the whole series of observations and for the distinctive model years. In particular, the provision capacity of N = 50 kW will amount on average 57% (208 days per year), and for the guaranteed component of N = 44 kW it will amount 62% (226 days per year). According to the research results, it is established that the optimal capacity of the hydropower plant is 50÷75 kW with a designed capacity utilization of 80÷70%, respectively. The approximate payback period will be 7-9 years with a 10% amortization rate, and accordingly a possible replacement of equipment in 10 years.

Publisher

O.M.Beketov National University of Urban Economy in Kharkiv

Subject

General Earth and Planetary Sciences,General Environmental Science

Reference15 articles.

1. Energy strategy of Ukraine for the period up to 2035. URL: http://zakon3.rada.gov.ua/laws/show/605-2017-%D1%80 [in Ukrainian]

2. Vasko, P.F. Current state and prospects of small hydropower development in Ukraine. URL: https://niss.gov.ua/sites/default/files/2014-06/0620_pres2.pdf [in Ukrainian]

3. Vlasyuk, Yu.S., Stefanishin, D.V. (2018). On the problems and prospects of small hydropower in Ukraine. Mathematical modeling in economics, 1(10), 126–138. [in Ukrainian]

4. Small hydropower plants of Ukraine. URL: Retrieved from: https://uk.wikipedia.org/wiki/%D0%9C%D0%B0%D0%BB%D1%96_%D0%93%D0%95%D0%A1_%D0%A3%D0%BA%D1%80%D0%B0%D1%97%D0%BD%D0%B8 [in Ukrainian]

5. Stefanishin, D.V., Vlasyuk, Yu.S. (2018). On the question of comparative analysis of hydropower characteristics of small and large hydropower plants of Ukraine as part of hydro units with reservoirs. Mathematical modeling in economics, 2(11), 71–83. [in Ukrainian]

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3