Openwork scheduling for steep-grade iron-ore deposits with the help of near-vertical layers

Author:

Panchenko ValeriiORCID

Abstract

Purpose is to develop efficient scheduling to excavate steep-grade iron-ore deposits using near-vertical layers relying upon production practices by an open pit of Poltava Mining-and-Processing Integrated Works (MPIW). Methods. The goal achievement involved system analysis of openwork scheduling for steep-grade iron-ore deposits by means of near-vertical layers in an open pit of Poltava MPIW; the scheduling process was structured from the viewpoint of decision-making under uncertainty. Findings. New scheduling methods to excavate steep-grade iron-ore deposits by means of near-vertical layers have been developed. The methods have been represented in the informal (descriptive) structure being mandatory for further transition to formalization of certain stages of technological decision-making during scheduling. To improve the scheduling efficiency, it is recommended to prepare initial process data using K-MINE software; Deswik software is recommended to determine economic indices as well as pit outlines. Originality.For the first time ever, a new mechanism of expedient spatiotemporal control of the specific excavation volumes while varying both “starting” time and intensity of a layer mining has been identified for the traditional openwork. The mechanism makes it possible to implement piecewise stable dynamics of annual output. Moreover, it also helps solve inverse problem, i.e. determine target values of spatiotemporal controlled parameters (i.e. “starting” time and intensity of the layer mining) for the required dynamics of ore and overburden excavation amounts. Practical implications. The proposed methods concerning scheduling steep-grade iron-ore deposit mining using near-vertical layers relying upon production practices by an open pit of Poltava MPIW have been tested successfully. Their efficiency has been proved. Currently, they are the key procedures being applied to schedule extraction using near-vertical layers in the context of the considered open pit. Keywords: iron-ore deposits, openwork, steep-grade layers, scheduling

Publisher

Dnipro University of Technology

Subject

Geochemistry and Petrology,Geotechnical Engineering and Engineering Geology

Cited by 12 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. Monitoring and estimation of mining and geometric indicators of the deposit;IOP Conference Series: Earth and Environmental Science;2024-05-01

2. Strategic planning of open pit mining operations using the Micromine Beyond Optimiser;IOP Conference Series: Earth and Environmental Science;2024-05-01

3. Reduction of ore losses on the footwall by improving ore breaking;E3S Web of Conferences;2024

4. Geometrization of Kryvbas iron ore deposits;IOP Conference Series: Earth and Environmental Science;2023-10-01

5. Enhancement of the technology of caved ore drawing from the ore deposit footwall “triangle”;IOP Conference Series: Earth and Environmental Science;2023-10-01

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3