Determination of Critical Pattern of 60 Meter Ship Construction Project Using Precedence Diagram Method (PDM)

Author:

Sumantri Siswo Hadi1,Thamrin Suyono1,Putra Apriyanto I. Nengah1,Suhardono Edi1,Rudiawan Beny1,Susanto Arica Dwi2

Affiliation:

1. Indonesia Defense University, Sentul, Sukahati, Citeureup, Bogor, West Java, Indonesia

2. Indonesian Naval Technology College, STTAL, Bumimoro-Morokrembangan, Surabaya 60187, Indonesia

Abstract

PT. XYZ in Surabaya is engaged in the production of commercial ships, providing ship repair and maintenance services as well as general engineering with specifications based on orders. Along with the development of the technology industry, ship production requires every shipyard to evaluate the system used. The time delay is the problem of building a 60 meter commercial ship. The Precedence Diagram Method (PDM) is a method for scheduling project time and showing critical trajectories of project activities. The results showed that in the project scheduling, there are 13 activities that have a zero value or critical activity which are activities Hull Fabrication, Hull Sub Assembly, Hull Assembly, Hull Erection, Blasting and Painting Raw Material, Finishing Hull, Anode, Machinery Outfitting, Cabling, Computing and Information, Machinery Commisioning, Equipment Commisioning, Harbour Acceptance Test, Yard Trial, Delivery to Customer So that it needs more strict control and supervision from the contractor in carrying out the activities of the 60 meter commercial ship building project activities for each activity/activity so that it does not experience delays and the project can be completed on time.

Publisher

North Atlantic University Union (NAUN)

Subject

Management, Monitoring, Policy and Law,Geography, Planning and Development

Reference25 articles.

1. Agarwal, R. (2013). Critical Path Method in Designing Feasible Solutions. International Journal of Scientific Research and Reviews , 190-202.

2. Agyei, W. (2015). Project Planning And Scheduling Using PERT And CPM Techniques With Linear Programming: Case Study. INTERNATIONAL JOURNAL OF SCIENTIFIC & TECHNOLOGY RESEARCH , 222-227

3. Alecu, F. (2014). Cost Control and Performance Review of Software Projects by Using the Earned Value Management. Oeconomics of Knowledge , 2-6.

4. Andawei, M.-E. M. (2014). Extension of Time Determination in Construction Projects in Nigeria: The Critical Path Method. The International Journal Of Engineering And Science (IJES), 48-51.

5. Arica Dwi Susanto, A. A. (2018). The Optimization of Multipurpose Building Development on Project Scheduling Using Precedence Diagram Method (PDM). ASRO JOURNAL-STTAL, 9(1), 1-7.

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3