Ikonnikova A,Ikinnikov V,Panova A
Abstract
Abstract
Main difficulties, arising in the selection of a workers link, as well as changes in the parameters of the model, depending on the composition of the link in organizational and technological planning are discussed in this article. The results, obtained in the course of the study, are summarized in graphs. Variant modeling of the technological process complexes implementation consists in finding a variant of teams’ composition, taking into account their intra-team plans and combining them at the work fronts, where the indicators of production program (construction plan) will be the best one, according to a given criterion and restrictions on resources and conditions of the customer. Otherwise, construction period of the first option was 22.46 months: the duration of each subsequent house construction was 19.5 days longer than the previous one. In variants 2 and 3, this difference decreased to 14.5 days, and the total duration decreased by 4.88 months and amounted to 17.58 months.