Abstract
At present, the seismic performance of UHV transformers is mostly studied without considering the interaction between soil and superstructure. In practical engineering, the transformer is installed on the foundation slab buried in the soil. Under the action of earthquake, the interaction between the soil and the structure changes the earthquake response of the upper electrical structure. In order to study the influence of the interaction between soil and structure on the seismic performance of the transformer, the shaking table test method of simulated earthquake is used, and the shaking table test of UHV transformer with scale ratio of 1:4 is carried out in class I field conditions. The dynamic characteristics of the equipment and the seismic response of the bushing under different test conditions are obtained respectively. The test results show that when the peak acceleration is 1.2g, the acceleration response at each measuring point on the box is 1.63-1.92 times that when the peak acceleration is 0.4g. With the increase of seismic peak acceleration, the acceleration and strain increase of high voltage bushing are greater than that of medium and low voltage bushing, which has a great influence on the seismic response of high voltage bushing. The research conclusion can provide reference for substation engineering design.
Subject
General Physics and Astronomy
Reference12 articles.
1. Effects of sheds and cemented joints on seismic modelling of cylindrical porcelain electrical equipment in substations [J];Li;Earthquakes and Structures,2016
2. Study on Seismic Performance of Porcelain Pillar Electrical Equipment Based on Nonlinear Dynamic Theory[J];Xue;Advances in Civil Engineering,2021
3. During Wenchuan Earthquake [J];Power System Technology,2011
4. Tests and Analyses on Failure Mechanism of 1100 kV UHV Transformer Porcelain Bushing[J];Xie;High Voltage Engineering,2017