Hierarchical structure and transfer mechanism to assess the scheduling-related risk in construction of prefabricated buildings: an integrated ISM–MICMAC approach

Author:

Fan Cheng,Binchao Deng,Yin Yilin

Abstract

PurposeUnder the background that engineering, procurement and construction (EPC) contracting model is introduced to adapt to the highly fragmented characteristics of prefabricated construction, the schedule management of general contractor is faced with the challenge of dynamic transmission and interaction of construction scheduling-related risk. The purpose of this paper is to develop the hierarchy of prefabricated construction scheduling-related risks from the perspective of the general contractor, and to analyze the transmission mechanism between risks. The paper also aims to further distinguish the difference of the impact degree of scheduling-related risks, and provide reference for formulating the strategy to alleviate the construction delay.Design/methodology/approachBased on a review of the literature on prefabricated buildings, this paper identifies 22 scheduling-related risks in construction from the perspective of the general contractor. Semi-structured interviews were then conducted to obtain experts' views on the interrelationships among these risks. Following this, their overall structure was determined by using a hierarchical structure established by using interpretive structural modeling (ISM), and Matrice d'Impacts Croisés Multiplication Appliqués à un Classement (MICMAC) technique was applied to classify them into four groups according to their driving and dependence powers.FindingsThe results indicate that the 22 scheduling-related risks in construction followed the inherent path of step-by-step transmission, and all of them could cause different degrees of delays in prefabricated construction. Among them, general experience in contracting projects, the use of emerging technologies and the completeness of the relevant standards and specifications were strong drivers of scheduling delays in construction, and should be prioritized by the general contractor in schedule management. The transitive link between scheduling risks can guide them in developing prevention strategies.Research limitations/implicationsData quality and reliability risks are the major drawbacks of semi-structured interviews. These were minimized by engaging experts with rich theoretical and hands-on experience in prefabricated construction projects. The hierarchical model only reflects static influence relationships, and so dynamic interactions among scheduling-related risks should be studied in future.Originality/valueThe primary value of this study is in its development of a hierarchical model by using the integrated ISM–MICMAC approach that reflects the interaction between scheduling risks in the construction of prefabricated buildings. The hierarchy of these risks and the results of a “driving-dependence power” analysis can guide the general contractor in taking targeted preventive measures to avoid scheduling delays in the construction of prefabricated buildings.

Publisher

Emerald

Subject

General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering

Reference68 articles.

1. Factors affecting over economy of prefabricated construction systems;International Journal of Advanced Scientific Research and Management,2016

2. Supply chain risk factors in green construction of residential mega projects: interactions and categorization;Engineering Construction and Architectural Management,2021

3. A multi-objective GA-based optimization for holistic manufacturing, transportation and assembly of precast construction;Automation in Construction,2016

4. Analysis of interacting uncertainties in on-site and off-site activities: implications for hybrid construction;International Journal of Project Management,2016

5. Performance-based control of variability and tolerance in off-site manufacture and assembly: optimization of penalty on poor production quality;Construction Management and Economics,2020

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3