Wondimu Paulos Abebe,Hosseini Ali,Lohne Jadar,Laedre Ola
Abstract
Purpose
Early contractor involvement (ECI) faces many barriers when it is implemented in public procurement, given that it is different from traditional business practices. Primarily, public owners face a major challenge, as they should treat all bidders equally. The purpose of this paper is to explore suitable ECI approaches that public owners could use.
Design/methodology/approach
In addition to a literature and document study, 14 semi-structured in-depth interviews with key personnel from 11 cases selected from Norwegian public bridge projects were carried out.
Findings
In all, 23 unique approaches of ECI were identified during this research (16 from literature and 7 new from case projects). The findings provide a new direction to ECI through introducing new approaches of ECI from the case projects.
Originality/value
This paper for the first time presents several alternatives of ECI approaches for public owners with the intention of illustrating ECI is actually possible in the public project procurement. Furthermore, it presents for the first time success factors of ECI with the intention of increasing the understanding of ECI concept from a public procurement perspective.
Reference51 articles.
1. Flexible strategies for centralized public procurement;Review of Economics and Institutions,2010
2. Exploring critical success factors for partnering in construction projects;Journal of Construction Engineering and Management,2004
3. The implementation of building information modelling within an integrated public procurement approach: the main contractor’s perspective,2016
4. Improving collaboration in construction: an opportunity for action research,2013
Cited by
18 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献