Pararajasingam Ramgy,Waidyasekara Anuradha Samarajeewa,Victar Hasith Chathuranga
Abstract
Purpose
Construction material management plays a significant role in achieving successful project delivery of a construction project. However, ineffective material management is a critical issue in the construction industry, especially in developing economies, of which Sri Lanka is not an exception. Therefore, this study aims to focus on exploring the causes of ineffective material management practices in civil engineering construction projects in Sri Lanka and their impact on successful project delivery.
Design/methodology/approach
Furthermore, the literature findings were validated through the preliminary survey. Subsequently, a quantitative research approach was adopted to pursue the research aim. Questionnaire responses were obtained from 215 construction professionals in civil engineering projects who were selected using the judgemental and snowball sampling techniques. Collected data were analysed through Statistical Package for the Social Sciences (SPSS) V26 and Microsoft Excel 2016.
Findings
Moreover, the study revealed that material price fluctuation, shortage of material in the market, delay in material procurement, inadequate planning and delays in material delivery are the most frequent causes of ineffective material management in civil engineering projects. In addition, it was evidenced that most ineffective material management practices cause both time and cost overruns in civil engineering construction projects. Most respondents emphasized inadequate planning, inadequate qualified and experienced staff, lack of supervision and lack of leadership as the causes for both time and cost overruns.
Originality/value
The study was concluded by proposing strategies for effective material management. Education/training/enlightenment of staff in charge of materials management, use of software like Microsoft Project, Primavera and similar software to eliminate manual errors in material management, and providing clear specifications to suppliers were the most agreed strategies for effective material management in civil engineering construction projects.
Reference43 articles.
1. Importance of planning for the transport stage in procurement of construction materials,2014
2. Energy saving performance assessment and lessons learned from the operation of an active phase change materials system in a multi-storey building in Melbourne;Applied Energy,2019
3. The effect of poor materials management in the construction industry: a case study of Abuja, Nigeria;Acta Structilia,2021
4. Integrating quantitative and qualitative data in mixed methods research challenges and benefits;Journal of Education and Learning,2016
5. Arijeloye, B.T. and Akinradewo, F.O. (2016), “Assessment of materials management on building projects in Ondo state, Nigeria”, pp. 168-185, available at: www.researchgate.net/publication/308674624_Assessment_of_materials_management_on_building_projects_in_Ondo_State_Nigeria