Author:
Mahmood Ali,Abrishami Sepehr
Abstract
Purpose
The purpose of this paper is to determine whether the implementation of building information modelling (BIM) concepts of the various processes involved in building surveying practice can lead to a reduction in waste. In turn leading to a synergy between BIM functionalities and lean production concepts.
Design/methodology/approach
To verify and validate the existence of this synergy between the two methods in building surveying, evidences were gathered from previous literature that supports these interactions. Next, a questionnaire was conducted for the purpose of identifying new interactions and providing further evidence to support existing interactions. Finally, based on the findings from previous literature and the results of the questionnaire, an interaction matrix was constructed linking the two concepts with the relevant evidence found.
Findings
The results of the questionnaire show that the BIM functionality with the highest interactions, maintenance of information integrity, had a high correlation with the reduction of variability, cycle time, batch size and promoting standardization of value flow. 4 D model-based scheduling, the second highest functionality, showed a high correlation with the reduction of variability, cycle time, batch size and an increase in the use of visual management. Finally, the results of the interaction matrix between the two concepts showed that the BIM functionalities with the most interactions were maintenance of information integrity, visualization of form and the automated generation of models and documents. The lean principles with the most interactions were reducing variability, cycle time, batch size as well as “enables visual management”. While most of these interactions were positive, negative interactions were also observed. These negative interactions were due to the fact that the level of competency and knowledge in BIM for building surveyors is at reduced levels which can lead to increased human errors.
Originality/value
The significance of this study is to provide the basis for building surveying organizations who wish to implement BIM and how this would lead to a synergy between BIM functionalities and lean principles. Both positive and negative interactions were considered to provide these organizations with different options for waste elimination.
Subject
Building and Construction,Architecture,Civil and Structural Engineering,General Computer Science,Control and Systems Engineering
Reference114 articles.
1. Lean management and innovation performance: evidence from international manufacturing companies;Management Research Review,2019
2. Status of BIM adoption and the BIM experience of cost consultants in Australia;Journal of Professional Issues in Engineering Education and Practice,2014
3. Designing out construction waste using BIM technology: stakeholders’ expectations for industry deployment;Journal of Cleaner Production,2018
4. Clash detection or clash avoidance? An investigation into coordination problems in 3D BIM;Buildings,2017
5. Simulating the dynamics of social agents and information flows in BIM-based design;Automation in Construction,2018