Salama Tarek,Moselhi Osama
Abstract
Purpose
The purpose of this paper is to present a newly developed multi-objective optimization method for the time, cost and work interruptions for repetitive scheduling while considering uncertainties associated with different input parameters.
Design/methodology/approach
The design of the developed method is based on integrating six modules: uncertainty and defuzzification module using fuzzy set theory, schedule calculations module using the integration of linear scheduling method (LSM) and critical chain project management (CCPM), cost calculations module that considers direct and indirect costs, delay penalty, and work interruptions cost, multi-objective optimization module using Evolver © 7.5.2 as a genetic algorithm (GA) software, module for identifying multiple critical sequences and schedule buffers, and reporting module.
Findings
For duration optimization that utilizes fuzzy inputs without interruptions or adding buffers, duration and cost generated by the developed method are found to be 90 and 99 percent of those reported in the literature, respectively. For cost optimization that utilizes fuzzy inputs without interruptions, project duration generated by the developed method is found to be 93 percent of that reported in the literature after adding buffers. The developed method accelerates the generation of optimum schedules.
Originality/value
Unlike methods reported in the literature, the proposed method is the first multi-objective optimization method that integrates LSM and the CCPM. This method considers uncertainties of productivity rates, quantities and availability of resources while utilizing multi-objective GA function to minimize project duration, cost and work interruptions simultaneously. Schedule buffers are assigned whether optimized schedule allows for interruptions or not. This method considers delay and work interruption penalties, and bonus payments.
Subject
General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering
Reference35 articles.
1. Multi-objective genetic optimization for scheduling a multi-storey building;Automation in Construction,2014
2. Versatile multi-objective genetic optimization for non-identical multi-storey building projects,2015
3. Bakry, I. (2014), “Optimized scheduling of repetitive construction projects under uncertainty”, PhD thesis, Department of Building, Civil and Environmental Engineering, Concordia University, Montreal.
4. Bakry, I., Moselhi, O. and Zayed, T. (2016), “Optimized scheduling and buffering of repetitive construction projects under uncertainty”, Engineering, Construction and Architectural Management, Vol. 23 No. 6, pp. 782-800.
5. A two-phase GA model for resource-constrained project scheduling;Automation in Construction,2009