Author:
El-Sayegh Sameh Monir,Al-Haj Rana
Abstract
Purpose
The purpose of this paper is to propose a new framework for time–cost trade-off. The new framework provides the optimum time–cost value taking into account the float loss impact.
Design/methodology/approach
The stochastic framework uses Monte Carlo Simulation to calculate the effect of float loss on risk. This is later translated into an added cost to the trade-off problem. Five examples, from literature, are solved using the proposed framework to test the applicability of the developed framework.
Findings
The results confirmed the research hypothesis that the new optimum solution will be at a higher duration and cost but at a lower risk compared to traditional methods. The probabilities of finishing the project on time using the developed framework in all five cases were better than those using the classical deterministic optimization technique.
Originality/value
The objective of time–cost trade-off is to determine the optimum project duration corresponding to the minimum total cost. Time–cost trade-off techniques result in reducing the available float for noncritical activities and thus increasing the schedule risks. Existing deterministic optimization technique does not consider the impact of the float loss within the noncritical activities when the project duration is being crashed. The new framework allows project managers to exercise new trade-offs between time, cost and risk which will ultimately improve the chances of achieving project objectives.
Subject
Economics and Econometrics,Finance,Accounting,Business and International Management
Reference51 articles.
1. Non-dominated archiving multi-colony ant algorithm in time–cost trade-off optimization;Journal of Construction Engineering and Management,2009
2. Time-cost optimization model considering float-consumption impact;Journal of Construction Engineering and Management,2015
3. Float allocation using the total risk approach;Journal of Construction Engineering & Management,2009
4. Total float management for delay analysis;AACE International Transactions,2005
5. Float analysis of non-serial repetitive activities;Construction Management and Economics,2003