Abstract
Purpose
– The purpose of this paper is to study the use of the Lean Six Sigma (LSS) methodology in a construction company.
Design/methodology/approach
– In our study we analyze 62 LSS improvement projects carried out within a Dutch company. In our analysis we focus on both speed, in terms of throughput time (THT), and impact, in terms of project completion, of each project.
Findings
– From the analysis we conclude that the current THT of a project is about a year and we identify important factors that cause large project's THTs These factors are then translated into recommendations for an efficient execution of LSS improvement projects.
Research limitations/implications
– The analysis is based on a sample from one company of the Dutch construction industry. The scope should be broadened as more companies adopt quality and process improvement programs, such as LSS.
Originality/value
– The narrowed scope, only one company and focused mostly on the speed of projects, helped to do an in-depth analysis. Therefore, we are able to present concrete and useful recommendations that relate to practical issues in the execution of improvement projects. These recommendations offer a checklist for construction companies in the project selection process, in situations of starting or improving an LSS program
Reference35 articles.
1. Alwi, S.
,
Hampson, K.
and
Mohamed, S.
(2002), “Non value-adding activities: a comparative study of Indonesian and Australian construction projects”, Proceeding of the 10th Annual Conference on Lean Construction, IGLC, Gramado.
2. Antony, J.
(2004), “Pros and Cons of Six Sigma: an academic perspective”, TQM Magazine, Vol. 16 No. 4, pp. 303-306.
3. Arditi, D.
and
Gunaydin, H.M.
(1997), “Total quality management in the construction process”, International Journal of Project Management, Vol. 15 No. 4, pp. 235-243.
4. De Koning, H.
and
De Mast, J.
(2006), “A rational reconstruction of Six Sigma’s breakthrough cookbook”, International Journal of Quality and Reliability Management, Vol. 23 No. 7, pp. 766-787.
5. De Koning, H.
and
De Mast, J.
(2007), “The CTQ flowdown as a conceptual model of project objectives”, Quality Management Journal, Vol. 14 No. 2, pp. 19-28.
Cited by
29 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献