Substantial changes were made on many UK construction projects in response to the COVID-19 pandemic. The purpose of this paper is to explore the unanticipated positive consequences of these and the scope for longer-term learning and developments within the sector.
Design/methodology/approach
A qualitative approach was used, semi-structured interviews were conducted across six major project sites. Interviewees (n = 33) included site and senior managers, supply chain representatives and occupational safety and health (OSH) professionals. The interviews explored their experiences of working on site during the pandemic, the changes made to work practices and their perceived impacts of these changes.
Findings
Improved planning and work sequencing were part of the revised process to make sites COVID-secure. This increased worker effectiveness and housekeeping/tidiness. The view on some sites was that this would improve OSH performance. The changes were perceived to be beneficial but may not be accepted by clients in the long term, as they could result in projects taking longer to complete. The ways in which COVID-19 risk has been communicated and perceived also provides longer-term lessons for the sector’s OSH management and training.
Originality/value
Construction has adapted rapidly and effectively to new ways of working during the pandemic. This research captured in real time some of the changes made and presents an argument for embedding and adopting the changes to improve working arrangements and OSH within the construction sector.
Reference82 articles.
1. The COVID-19 pandemic calls for spatial distancing and social closeness: not for social distancing!;International Journal of Public Health,2020
2. Analysis of occupational accidents induced human injuries: a case study in construction industries and sites;Journal of Civil Engineering and Construction Technology,2016
3. The impact of COVID-19 pandemic on Jordanian civil engineers and construction industry;International Journal of Engineering Research and Technology,2020
4. Covid-19 causes of delays on construction projects in Kuwait;International Journal of Engineering Research and General Science,2020
5. Physical distancing or social distancing: that is the question;Canadian Journal of Anesthesia/Journal Canadien D'anesthésie,2020
Cited by
15 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献