Author:
Islam Muhammad Saiful,Nepal Madhav,Skitmore Martin
Abstract
Purpose
Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural relationships among each other. The purpose of this study is, therefore, to establish the complex structural relationships of risks involved.
Design/methodology/approach
In total, 76 published articles from the previous literature are reviewed using the content analysis method. Three risk networks in different phases of power plant projects are depicted based on literature review and case studies. The possible methods of solving these risk networks are also discussed.
Findings
The study finds critical cost overrun risks and develops risk networks for the procurement, civil and mechanical works of power plant projects. It identifies potential models to assess cost overrun risks based on the developed risk networks. The literature review also revealed some research gaps in the cost overrun risk management of power plants and similar infrastructure projects.
Practical implications
This study will assist project risk managers to understand the potential risks and their relationships to prevent and mitigate cost overruns for future power plant projects. It will also facilitate decision-makers developing a risk management framework and controlling projects’ cost overruns.
Originality/value
The study presents conceptual risk networks in different phases of power plant projects for comprehending the root causes of cost overruns. A comparative discussion of the relevant models available in the literature is presented, where their potential applications, limitations and further improvement areas are discussed to solve the developed risk networks for modeling cost overrun risks.
Subject
Building and Construction,Architecture,Civil and Structural Engineering,General Computer Science,Control and Systems Engineering
Reference76 articles.
1. Factors affecting construction labour productivity for Malaysian residential projects;Structural Survey,2005
2. Causes of delay in Mara management procurement construction projects;Journal of Surveying, Construction and Property,2010
3. A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies: cost overrun in construction projects;International Journal of Managing Projects in Business,2021
4. Determinants of the performance of public sector development projects;International Journal of Management,2012
5. Causes, effects, benefits, and remedies of change orders on public construction projects in Oman;Journal of Construction Engineering and Management,2014
Cited by
2 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献