Structuring risks for a comprehensive understanding of cost overruns in power plant projects

Author:

Islam Muhammad Saiful,Nepal Madhav,Skitmore Martin

Abstract

Purpose Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural relationships among each other. The purpose of this study is, therefore, to establish the complex structural relationships of risks involved. Design/methodology/approach In total, 76 published articles from the previous literature are reviewed using the content analysis method. Three risk networks in different phases of power plant projects are depicted based on literature review and case studies. The possible methods of solving these risk networks are also discussed. Findings The study finds critical cost overrun risks and develops risk networks for the procurement, civil and mechanical works of power plant projects. It identifies potential models to assess cost overrun risks based on the developed risk networks. The literature review also revealed some research gaps in the cost overrun risk management of power plants and similar infrastructure projects. Practical implications This study will assist project risk managers to understand the potential risks and their relationships to prevent and mitigate cost overruns for future power plant projects. It will also facilitate decision-makers developing a risk management framework and controlling projects’ cost overruns. Originality/value The study presents conceptual risk networks in different phases of power plant projects for comprehending the root causes of cost overruns. A comparative discussion of the relevant models available in the literature is presented, where their potential applications, limitations and further improvement areas are discussed to solve the developed risk networks for modeling cost overrun risks.

Publisher

Emerald

Subject

Building and Construction,Architecture,Civil and Structural Engineering,General Computer Science,Control and Systems Engineering

Reference76 articles.

1. Factors affecting construction labour productivity for Malaysian residential projects;Structural Survey,2005

2. Causes of delay in Mara management procurement construction projects;Journal of Surveying, Construction and Property,2010

3. A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies: cost overrun in construction projects;International Journal of Managing Projects in Business,2021

4. Determinants of the performance of public sector development projects;International Journal of Management,2012

5. Causes, effects, benefits, and remedies of change orders on public construction projects in Oman;Journal of Construction Engineering and Management,2014

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

1. In-Depth Analysis of Risks and Their Impacts on Solar Power Project Development: Public and Private Contractors’ Perspective;Journal of Legal Affairs and Dispute Resolution in Engineering and Construction;2024-11

2. Cost and time risk factors in construction projects in the Dominican Republic;Frontiers in Built Environment;2024-07-16

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3