Abstract
Purpose
Construction project management outcomes in the literature typically portray significant deviations from expected outcomes. Various theories from studies that focus superficially on causes of project cost and time overruns rather than root causes have not addressed this problem. The need is for a better understanding of how procurement strategy provides a fundamental means to address this problem. The purpose of this paper is to examine the procurement strategy used to deliver a new universities project in South Africa within budget and to ascertain its influence on the outcomes.
Design/methodology/approach
A case study was designed to provide a comprehensive and intensive methodology to identify and examine the construction procurement strategy and its influence on the project outcomes. Document analyses and semi-structured interviews were used to collect data on the construction procurement strategy and outcomes from the client team.
Findings
The evidence brought forward demonstrates that the successful outcome was largely a consequence of the client team, procurement strategy and systems of delivery. However, the collaborative procurement strategy formed the basis of the successful project delivery and outcomes. A general observation from the data is that an appropriate construction procurement strategy developed by an experienced client team and proactively implemented by an integrated delivery team working collaboratively is likely to achieve the intended project outcomes.
Practical implications
The findings show three critical keys to achieving intended outcomes – people, procurement strategy and systems of delivery at the governance, portfolio, programme and project management levels.
Originality/value
The value of this paper lies in using a comprehensive methodology to study the relationship between procurement strategy and outcomes. The findings can be applied by client teams to achieve better outcomes and value for money in infrastructure projects.
Subject
General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering
Reference58 articles.
1. Rethinking construction cost overruns: cognition, learning and estimation;Journal of Financial Management of Property and Construction,2014
2. Significant factors causing cost overruns in telecommunication projects in Nigeria;Journal of Construction in Developing Contries,2010
3. How to plan and perform a qualitative study using content analysis;Nursing Plus Open,2016
4. Three-stage least-squares analysis of time and cost overruns in construction contracts;Journal of Construction Engineering and Management,2010
5. Document analysis as a qualitative research method;Qualitative Research Journal,2009
Cited by
11 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献