Abstract
Purpose
Large-scale projects are the typical delivery model in the engineering and construction industry, with their very own characteristics. Even though well established, only 1 in 1,000 large-scale projects is successful (Flyvbjerg, 2011). A lack of effective supply chain risk management (SCRM) has repeatedly been identified as one of the main causes. While the SCRM body of knowledge seems increasingly well established, a lack of effective methods meeting the specific requirements of large-scale projects can be observed.
Design/methodology/approach
This paper presents a structured and prioritized view on the supply chain risk portfolio in this sector: first, the authors identified and categorized the key supply chain risks in the recent literature. Next, the authors surveyed large-scale project managers across multiple industries, mainly coming from the domains of supply chain management and project management. Finally, the authors provide a contextualized risk taxonomy for engineering, procurement and construction (EPC) projects.
Findings
The identified risk portfolio deviates from generic projects significantly and shows a very high inherent risk exposure of large-scale projects. In particular, behavioral risks are identified as crucial. Additionally, a bias to considerably underestimate risks at project beginning is found.
Originality/value
The contextualized SCRM taxonomy offers a systematic and structured view on the key supply chain risks in EPC large-scale projects. The identified risks are considerably different in their characteristics compared to generic projects or classical SCRM approaches. The authors thus provide a new perspective on SCRM in this specific setting and complement traditional risk and project risk management techniques.
Subject
General Business, Management and Accounting