Author:
Roy Soumen Kumar,Sarkar A.K.,Mahanty Biswajit
Abstract
Purpose
The purpose of this paper is to study the effect of a critical subsystem development indigenously on the outcome of an Indian defence R&D project. Indigenous development of the critical subsystem requires the development of a number of technologies; hence the study is taken up for indigenously development of critical subsystem.
Design/methodology/approach
A simulation-based approach is used in this paper for studying the effect of indigenization decisions. A defence R&D project with the critical subsystems is modeled in Graphical Evolution and Review Technique (GERT) networks, and simulated in Arena simulation software using discrete event simulation model. The simulation model is thereafter experimented with decision options for the critical subsystem. Data were collected from the project management office (PMO) of short range homing guided missile (SRHGM) for this simulation study.
Findings
It has been found in this case that timely development of technology plays a key role in the Indian defence R&D projects. While indigenization of critical components reduces cost of development, the trade-off lies in much increased project development time. It is imperative that project teams should identify critical components early and work out appropriate strategies of indigenous development to avoid time overrun of the projects.
Research limitations/implications
The accuracy of results of the study could perhaps be affected on account of the extent of data forthcoming from the PMO. However, GERT framework presented in this paper is realistically derived from the practices used in the SRHGM project.
Originality/value
The study would help the project teams to identify critical subsystems early and work out appropriate strategies of indigenous development to avoid time overrun of the projects. This study would also make the project as well as the R&D teams aware of the causes for delays and cost overruns, and assist to deliver a product meeting end-user requirements.
Reference15 articles.
1. Practical proposals for managing uncertainty and risk in project planning;International Journal of Project Management,1998
2. An Algebra for the analysis of generalized activity network;Management Science,1968
3. Capacity-building in defence science and technology: a perspective from the DRDO;Strategic Analysis,2008
Cited by
2 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献