Production planning, monitoring and review: comparison between the practices in an urban rail transit megaproject with the Last Planner System

Author:

Belayutham SheilaORCID,Mohamad Jaafar Rabiatul Nurul Akmar,Ismail Herda Balqis,Che Ibrahim Che Khairil IzamORCID

Abstract

PurposeMegaprojects are typically very expensive public-centred projects that leave little space for any mismanagement or deficient planning, which could affect the project adversely. The Last Planner™ System (LPS) is a lean construction planning and control tool that functions to reduce waste and increase performance. Given the benefits, the application of the LPS in megaprojects is still scarce, especially in Malaysia. Hence, this study aims to compare the current production planning, monitoring and review practices in a megaproject with the LPS in order to explore the possibilities of adapting the LPS to the current practices.Design/methodology/approachThis longitudinal case-based study has first explored the current practices implemented in an infrastructure megaproject, which is an urban rapid transit (URT) project, which was then compared to the standard LPS practices. The case study has adopted several research methods such as observation, interview and document review.FindingsFindings from the study highlight that the current production planning, monitoring and review practices in the URT project mostly differs from the standard LPS practices with only slight similarities found in the major planning phases. The comparative study, which based on five reference points through master, phase, look-ahead, weekly work plan and measure, and learning has resulted in several key elements, representative of the different planning phases, such as collaborative programming, reverse planning, reliability, dependability and continuous learning.Practical implicationsThis study provides an alternative perspective to rail planners, as well as other types of project planners in considering the use of the LPS to enhance the quality of planning, monitoring and review in projects. The framework that highlights the core values and key elements for the related planning phases enables project teams with no lean background to partially adapt their current practices to the LPS with minimal disruption.Originality/valueThis study first contributes to the body of knowledge, where limited study was found comparing and contrasting current production planning practices against the LPS, particularly in rail-based megaproject. The results from the comparison are the key elements representing each of the planning phases that was rooted back to the core values (teamwork, involvement and collaboration, communication and transparency, and continuous improvement) necessary to enhance the current practices.

Publisher

Emerald

Subject

Strategy and Management,General Business, Management and Accounting,Business and International Management,General Decision Sciences

Reference46 articles.

1. Implementing Lean Production Strategies in Construction Companies,2003

2. Last planner system: experiences from pilot implementation in the Middle East,2009

3. Implementation of lean practices in the construction industry: a systematic review;Building and Environment,2019

4. Improving EPC performance,1993

Cited by 2 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3