Özyürek İbrahim,Erdal Mürsel
Abstract
Purpose
In Turkish public procurement practice of construction works, only bidders whose capabilities on each qualification criteria meet prescribed thresholds are taken into evaluation; however, final evaluation disregards contribution of contractor’s abilities to the delivery of project. The purpose of this study is to assign reasonable weights to qualification criteria stated in Public Procurement Law applicable for work contracts by the method of analytical hierarchy process (AHP) with crisp and fuzzy numbers and evaluate the results. Having optimum quality structures to obtain value for money and giving weight to environmental concern in tender evaluation stage can assist sustainable economy.
Design/methodology/approach
To introduce qualifications of tenderers to evaluation process, a survey was conducted among 20 public procurement specialists at Public Procurement Authority of Turkey. AHP and fuzzy analytical hierarchy process (FAHP) methods were used to obtain the weights for qualifications.
Findings
In any method used in the study, experience became the most important criterion after bid price. Facility, machine and equipment criterion became the second and annual turnover criterion became the third most important criterion.
Research limitations/implications
The set of qualification criteria used in this study is confined by Turkish Public Procurement Law and secondary regulations. However, as Public Procurement Law is in accordance with European Union directives, the conclusions of the study should not be considered to be geographically limited by the borders of Turkey. Also, professional to take part in the survey were randomly selected from the Public Procurement Specialist working at Public Procurement Authority.
Social implications
The outcomes of the study may improve sustainability through public procurement.
Originality/value
To the best of the authors’ knowledge, this is the first study offering weights for tenderer’s qualifications to be used in a multi-criteria decision-making process for contractor selection in public work procurement process in Turkey.
Reference34 articles.
1. Fuzzy decision support model for the selection of contractor in construction works;Journal of Construction,2018
2. Analysis of criteria influencing contractor selection using TOPSIS method;IOP Conference Series: Materials Science and Engineering,2017
3. A fuzzy AHP approach for supplier selection problem: a case study in a gear motor company;International Journal of Managing Value and Supply Chains,2013
4. Tender evaluation and supplier selection methods in public procurement;Journal of Purchasing and Supply Management,2013
5. Fuzzy hierarchical analysis;Fuzzy Sets and Systems,1985
Cited by
1 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献