Othman Ayman Ahmed Ezzat,Youssef Lamis Yasser Wagih
Abstract
Purpose
This paper aims to develop a framework for implementing the integrated project delivery (IPD) approach during the design process in architecture design firms (ADFs) in Egypt.
Design/methodology/approach
A research methodology consists of literature review, case studies and survey questionnaire was designed to achieve the abovementioned aim. First, literature review was used to identify and categorise the challenges of implementing IPD during the design process. Second, four case studies were analysed to investigate the values delivered to the client or missed due to the use of IPD or traditional procurement approaches, respectively. Finally, a survey questionnaire was carried out with a representative sample of ADFs in Egypt to investigate their perception towards the challenges of IPD implementation in Egypt. Based on the results of the above, the research developed a framework to facilitate the implementation of IPD in ADFs in Egypt.
Findings
Through literature review, the research identified 30 challenges that hamper the implementation of IPD in ADFs. These challenges were categorised due to their nature into five groups, namely, integration, cooperation, commitment and trust challenges, knowledge, experience skills and decision-making challenges, cultural challenges, legal and contractual challenges and technical and financial challenges. Results of data analysis showed that “poor communication and spirit of collaboration between project stakeholders” was ranked the highest influential challenge as IPD is based on collaboration and trust between project participants. In addition, “lack of training and motivation in investing for using IPD” was ranked the lowest influential challenge due to the poor attention paid to training in the construction industry. Moreover, despite the benefits of IPD implementations in many countries worldwide, it is not implemented in the Egyptian context. This necessitated taking action towards developing a framework to facilitate IPD implementation in ADFs in Egypt.
Research limitations/implications
The research focussed on ADFs in Egypt.
Practical implications
Adopting the proposed framework developed through this research will help implementing IPD during the design process in ADFs.
Originality/value
The research identified, categorised and analysed the challenges that obstruct the implementation of IPD in ADFs. The research tackled a topic that received scant attention in construction literature in the Middle East generally and Egypt in particular. In addition, this paper presented a framework to facilitate the implementation of IPD during the design process, which represents a synthesis that is novel and creative in thought and adds value to the knowledge in a manner that has not previously occurred.
Reference92 articles.
1. Comparison of the performance of traditional and direct labour methods of project procurement: a case study of some selected projects of the Nigerian army;Ethiopian Journal of Environmental Studies and Management,2013
2. Analysis of client-satisfaction factors in construction industry;Journal of Management in Engineering,1995
3. An analytical study of the current status of managing change orders during the construction phase of governmental projects in Egypt;Mansoura Engineering Journal (MEJ),2016
4. AIA (2007), “Integrated project delivery: a guide. American Institute of architects”, www.msa-ipd.com/IPD_Guide_2007.pdf (accessed 2 February 2020).
5. Integrated project delivery: case studies. 2010. AIA National. AIA California Council;AIA,2010
Cited by
20 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献