Author:
A. Kassem Mukhtar,Khoiry Muhamad Azry,Hamzah Noraini
Abstract
Purpose
This study aims to investigate the risk factors in construction projects in oil and gas processing facilities in Yemen and serves as a case study for developing countries.
Design/methodology/approach
By using a questionnaire, data were collected from 201 project managers and engineers employed in different sectors in the oil and gas industry in Yemen.
Findings
The survey analysis based on Kruskal–Wallis test method shows a high degree of agreement on the perceptions of risk factors depending on categories of companies. In other words, the tested risk factors exist in all sectors of oil companies in Yemen and are valid as a measure of risk factors in construction projects in oil and gas organizations in general. Although no evidence suggests that the risk factors differ significantly according to job title, the result of identifiable risk factors according to experience shows a statistically significant difference among participants in terms of their experience. The relative importance of the ranking of risk factors was obtained by the statistical analysis of responses on the impact and likelihood of occurrence of these risks. Findings show that internal risks are the greatest influential factors in construction projects in the oil and gas sector, followed by changes during construction project, government instability, incorrect project cost estimation, government delay in decision making, incorrect project schedule estimation, and political situation and war in the country.
Originality/value
These findings are valuable to organizations that are planning to conduct construction projects for oil and gas processing facilities in Yemen and other nations with similar environments, such as developing countries.
Subject
Strategy and Management,General Energy
Reference49 articles.
1. Risk analysis for the major factors affecting the construction industry in Jordan;Emirates Journal for Engineering Research,2005
2. Risk impact assessments in project budget development: quantity surveyors’ perspectives;International Journal of Construction Management,2018
3. Challenges of mega construction projects in developing countries;Organization, Technology and Management in Construction,2013
4. Risk analysis and management in construction;International Journal of Project Management,1997
5. The significant factors causing delay of building construction projects in Malaysia;Engineering, Construction and Architectural Management,2007
Cited by
31 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献