Al-Fadhali Najib,Mansir Dodo,Zainal Rozlin
Abstract
Purpose
Influential factors attributed to causing project completion delay (PCD) differ because of prevailing variability of local conditions. Construction projects specifically in Yemen (and other developing countries) experience devastating effects of PCD which include litigation, cost overrun, arbitration, abandonment and failure. While existing works have investigated the causes and effects of PCD, not much exist on approaches to optimizing its occurrence in Yemen. In a bid to enhance the effects of PCD in Yemen, the integrated influential factors (IIFs), which is a construction-party specific model, was developed to mitigate the effects of PCD in Yemen. As a build up to the development of this model, this paper aims to validate the IIFs model with a view to foster its application to enhance PCD in construction project delivery in Yemen.
Design/methodology/approach
The validation of the IIFs model was done through seeking the opinions of 12 selected construction industry experts. This involved using a structured questionnaire to seek information on the sustainability of implementing the IIFs model.
Findings
The findings revealed that if the IIFs model is vigorously implemented, it would go a long way in curbing delay in the delivery of construction projects, making construction delivery less risky due to the effects of delay.
Research limitations/implications
The study is limited to only influential factors of internal stakeholders of the construction phase. Similarly, the study was only conducted in the state of Sana'a, Yemen. The implication of the adoption of the IIFs model is that it can hopefully serve as an adaptive controller to construction project delivery relative to the specific parameters and factors investigated in this study.
Originality/value
The IIFs model is a novel approach to optimizing PCD in Yemen specific to both the construction-phase and internal stakeholders. Existing studies on PCD in Yemen, although investigating the causes and effect of PCD, hardly proffer any approach to optimizing PCD for successful construction project delivery.
Reference56 articles.
1. Delay and cost overrun in infrastructure projects in Jordan;Procedia Engineering,2017
2. Determining critical success factors of project management practice: a conceptual framework;Procedia – Social and Behavioral Sciences,2014
3. A framework for identifying causal factors of delay in nuclear power plant projects;Procedia Engineering,2016