Abstract
Purpose
All industry has been facing tremendous pressure since the beginning of 2020 owing to COVID-19 crisis, including real estate construction. The research is a case study investigating challenges and action plans faced by stakeholders (developers/consultants/contractors) in real estate construction in some major cities in Indonesia. This study aims to identify and prioritize on action plans related to real estate construction stakeholders.
Design/methodology/approach
The study gathered challenges and action plans by distributing open questionnaire to expert to get insights in their own verbatim. Data reduction was then performed to get high-level challenges and high-level action plans. High-level action plans were then analyzed using proposed Eisenhower-simultaneous importance performance analysis (SIPA) matrix which help prioritize high-level action plans. Correlation matrix was also constructed to gain insight on relation between action plans to challenges and to three main LEAN elements (Muda, Mura and Muri). Alternative ranking method using “sum-product to 3M” approach was also performed to give complementary insights.
Findings
Ten action plans fall under category “Act now and become COVID-19 champion company.” One falls under category “prepare and invest now to gain competitive advantage,” one falls under category “external collaboration now to survive,” one falls under category “external collaboration for potential efficiency,” whereas the remaining six action plans fall under category “let-it-go” or “do-nothing.”
Research limitations/implications
The study gathered only 48 and 64 respondents in its first and second questionnaires. Despite small number, the respondents are experts in their own field, and their valuable insights and responses off-set the limited number of participants. The study gives insightful action plans that can be taken by stakeholders in real-estate construction in Indonesia’s major cities analyzed by proposed Eisenhower-SIPA matrix.
Originality/value
The novelty of the research lies in the insights from industry experts in dealing with current COVID-19 pandemic in real-estate construction in Indonesia. Added value is also given through the use of Eisenhower-SIPA matrix.
Reference30 articles.
1. Barriers to adopting lean construction in the construction industry: a literature review;International Journal of Lean Six Sigma,2020
2. Lean construction in civil engineering and project management: case study analysis of UT Arlington college park;American Journal of Civil Engineering,2015
3. Eisenhower box for prioritising waiting list of orthodontic patients;Ohdm,2017
4. Building marketing strategies for state-owned enterprises against private ones based on the perspectives of customer satisfaction and service quality;Journal of Retailing and Consumer Services,2006
Cited by
24 articles.
订阅此论文施引文献
订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献