Schedule compression and emerging waste in construction: an assessment of overlapping activities

Author:

Salhab DianaORCID,Lindhard Søren MunchORCID,Hamzeh FarookORCID

Abstract

PurposeCompressing the schedule by using overlapping activities is a commonly adopted approach for accelerating projects. However, this approach might channel a variety of risks into the construction processes. Risks imply waste; still, evaluating the effects of using overlapping activities on schedule quality has been a looming gap in construction research. Therefore, this paper aims to study the quality of overlapping in terms of emerging waste and to demarcate the boundaries of the overlapping envelope.Design/methodology/approachThis study presents a method for assessing the consequences of implementing overlapping activities in a schedule on two types of waste namely waiting time and variation gap. A critical path method (CPM) network including eleven activities is modeled stochastically where the durations of individual activities are sampled as beta-distributions. Using program evaluation and review technique (PERT) assumptions to calculate the schedule dates, the network is simulated for various amounts of overlapping and the corresponding waste is quantified each time.FindingsResults show that not only the returns on overlapping are diminishing after a certain overlap percentage, but also waste in the production system increases. Particularly, results reveal that compressing the schedule leads to a decrease in variation gaps, but at the same time, it leads to a larger increase in waiting times, which creates more waste.Originality/valueThe presented study shows through simulation how overlapping activities affects productivity by identifying wastes. It shows that despite the apparent gains, overlaps should be used with caution, and while considering the side-effects of increased waste which introduces a need for increased managerial awareness.

Publisher

Emerald

Subject

General Business, Management and Accounting,Building and Construction,Architecture,Civil and Structural Engineering

Reference33 articles.

1. Flexible activity relations to support optimum schedule acceleration;Journal of Construction Engineering and Management,2016

2. Construction project evaluation using CPM-Crashing, CPM-PERT and CCPM for minimize project delays;Journal of Physics: Conference Series,2021

3. Analysis of workflow variability and its impacts on productivity and performance in construction of multistory buildings;Journal of Management in Engineering,2015

4. Modelling the boundaries of project fast-tracking;Automation in Construction,2017

5. Schedule compression of construction project: a review,2019

Cited by 1 articles. 订阅此论文施引文献 订阅此论文施引文献,注册后可以免费订阅5篇论文的施引文献,订阅后可以查看论文全部施引文献

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3