Abstract
PurposeThis paper aims to investigate the challenges faced by the transport infrastructure sector in its civil construction material supply processes, following the 2016 Kaikoura earthquake in New Zealand.Design/methodology/approachA case study approach was adopted, which included on-site observations, semi-structured interviews and literature-based desktop reviews.FindingsThe research findings show that there were supply problems for aggregates, concrete, stormwater pipes and some specialised products for the repair and rebuild of transport facilities. Those supply problems were largely caused by (1) difficulty in predicting material requirements, (2) constrained supply capability, (3) inadequate local freight capacity, (4) legal, cultural and/or environmental considerations on resource exploitation and utilisation, (5) impacts of COVID-19 and (6) ineffective communication and coordination.Research limitations/implicationsFor future research, it is recommended that a comparative analysis of multiple disaster cases be undertaken to further explore the generalisability of the research findings.Originality/valueThe research findings will inform the development of post-earthquake recovery policies and material supply chain operation strategies, in order to expedite the recovery of transport networks if a future earthquake strikes.