Abstract
Abstract
The problem considered in the paper is motivated by production planning in a foundry equipped with a furnace and a casting line, which provides a variety of castings in various grades of cast iron/steel for a large number of customers. The goal is to create the order of the melted metal loads to prevent delays in delivery of goods to customers. This problem is generally considered as a lot-sizing and scheduling problem. However, contrary to the classic approach, we assumed the fuzzy nature of the demand set for a given day. The paper describes a genetic algorithm adapted to take into account the fuzzy parameters of simultaneous grouping and scheduling tasks and presents the results achieved by the algorithm for example test problem.
Subject
Metals and Alloys,Industrial and Manufacturing Engineering